Home
Class 7
MATHS
A and B together can complete a piece of...

A and B together can complete a piece of work in 16 days while B and C together can complete the same work in 12 days and A and C together in 24 days. Find out the number of days that A will take to compete the work, working alone.

A

36 days

B

48 days

C

96 days

D

80 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by A, B, and C together and then isolate A's work. ### Step 1: Calculate the work done by A and B together. A and B together can complete the work in 16 days. Therefore, their combined work rate is: \[ \text{Work rate of A and B} = \frac{1}{16} \text{ (work per day)} \] ### Step 2: Calculate the work done by B and C together. B and C together can complete the work in 12 days. Therefore, their combined work rate is: \[ \text{Work rate of B and C} = \frac{1}{12} \text{ (work per day)} \] ### Step 3: Calculate the work done by A and C together. A and C together can complete the work in 24 days. Therefore, their combined work rate is: \[ \text{Work rate of A and C} = \frac{1}{24} \text{ (work per day)} \] ### Step 4: Set up the equations for total work rates. Let the work rates of A, B, and C be \( a \), \( b \), and \( c \) respectively. We can write the following equations based on the work rates: 1. \( a + b = \frac{1}{16} \) (Equation 1) 2. \( b + c = \frac{1}{12} \) (Equation 2) 3. \( a + c = \frac{1}{24} \) (Equation 3) ### Step 5: Add all three equations. Adding all three equations gives: \[ (a + b) + (b + c) + (a + c) = \frac{1}{16} + \frac{1}{12} + \frac{1}{24} \] This simplifies to: \[ 2a + 2b + 2c = \frac{1}{16} + \frac{1}{12} + \frac{1}{24} \] ### Step 6: Find a common denominator and simplify. The least common multiple of 16, 12, and 24 is 48. So, we convert each fraction: \[ \frac{1}{16} = \frac{3}{48}, \quad \frac{1}{12} = \frac{4}{48}, \quad \frac{1}{24} = \frac{2}{48} \] Adding these gives: \[ \frac{3}{48} + \frac{4}{48} + \frac{2}{48} = \frac{9}{48} \] Thus, we have: \[ 2a + 2b + 2c = \frac{9}{48} \] Dividing by 2: \[ a + b + c = \frac{9}{96} \] ### Step 7: Isolate A's work rate. Now, we can find A's work rate by subtracting the work rates of B and C from the total: 1. From Equation 2, we know \( b + c = \frac{1}{12} = \frac{4}{48} = \frac{8}{96} \). 2. Thus, we can find A's work rate: \[ a = (a + b + c) - (b + c) = \frac{9}{96} - \frac{8}{96} = \frac{1}{96} \] ### Step 8: Calculate the number of days A will take to complete the work alone. Since A's work rate is \( \frac{1}{96} \), it means A can complete the work alone in: \[ \text{Days taken by A} = \frac{1}{\frac{1}{96}} = 96 \text{ days} \] ### Final Answer: A will take 96 days to complete the work alone. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 13(b)|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • SIMPLE INTEREST

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet |10 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 18|10 Videos

Similar Questions

Explore conceptually related problems

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.

A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.

A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

Knowledge Check

  • A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

    A
    80 days
    B
    100 days
    C
    120 days
    D
    150 days
  • A and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.

    A
    12 days
    B
    14 days
    C
    16 days
    D
    18 days
  • A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

    A
    `(120)/(13)` days
    B
    `(480)/(13)` days
    C
    `(240)/(13)` days
    D
    `(960)/(13)` days
  • S CHAND IIT JEE FOUNDATION-TIME AND WORK -Question Bank - 13(a)
    1. A and B together can complete a piece of work in 16 days while B and C...

      Text Solution

      |

    2. A and B together can do a piece of work in 8 days. B alone can do it i...

      Text Solution

      |

    3. A man and a boy can do a piece of work in 24 days. If the man works al...

      Text Solution

      |

    4. A and B can do a piece of work in 30 days, while B and C can do the...

      Text Solution

      |

    5. A and B can do a job together in 7 days. A is 1 3/4 times as efficient...

      Text Solution

      |

    6. I can do a piece of work in 8 days, which can be done by you in 10 day...

      Text Solution

      |

    7. X is twice as good as a workman as Y. X finished a piece of work in 3 ...

      Text Solution

      |

    8. A can cultivate 2/5 the of a land in 6 days and B can cultivate 1/3 rd...

      Text Solution

      |

    9. The time taken by 4 men to complete a job is double the time taken by ...

      Text Solution

      |

    10. A , B and C can do a piece of work in 11 days, 20 days and 55 days re...

      Text Solution

      |

    11. A can do a piece of work in 20 days and B in 40 days. A begins the wor...

      Text Solution

      |

    12. A can complete a work in 9 days, B in 10 days and C in 15 days. B and ...

      Text Solution

      |

    13. A can do a piece of work in 4 hours, B and C together in 3 hours, a...

      Text Solution

      |

    14. Ram can do a piece of work in 6 days and Shyam can finish the same wor...

      Text Solution

      |

    15. A is twice as fast a workman as B and together they finish a piece of ...

      Text Solution

      |

    16. A does half as much work as B in one-sixth of the time.If together the...

      Text Solution

      |

    17. A work could be completed in 100 days by some workers. However, due to...

      Text Solution

      |

    18. A man and a boy received 800 as wages for 5 days for the work they ...

      Text Solution

      |

    19. a certain number of persons can complete a piece of work in 55 days. I...

      Text Solution

      |

    20. A can complete a work in 18 days, B can do the same work in half the t...

      Text Solution

      |