A manufactures makes two products, A and B. Product A sell at Rs. 200 each and takes `1/2` hours to make. Product B shell at Rs. 300 each and takes 1 hour to make. There is a permanent order for 14 of product A and 16 of product B.A working week consists of 40 hours of production and the weekly turnover must not be less than Rs. 10000. If the profit on each of the product A is Rs.20 and on product B, it is Rs.30 then how many of each should be produced so that the profit is maximum? Asso, find the maximum profit.
A manufactures makes two products, A and B. Product A sell at Rs. 200 each and takes `1/2` hours to make. Product B shell at Rs. 300 each and takes 1 hour to make. There is a permanent order for 14 of product A and 16 of product B.A working week consists of 40 hours of production and the weekly turnover must not be less than Rs. 10000. If the profit on each of the product A is Rs.20 and on product B, it is Rs.30 then how many of each should be produced so that the profit is maximum? Asso, find the maximum profit.
Text Solution
AI Generated Solution
The correct Answer is:
To solve the problem of maximizing profit for the manufacturer producing products A and B, we will follow these steps:
### Step 1: Define the Variables
Let:
- \( x \) = number of units produced of product A
- \( y \) = number of units produced of product B
### Step 2: Formulate the Objective Function
The profit from product A is Rs. 20 per unit, and from product B is Rs. 30 per unit. Therefore, the objective function to maximize profit \( Z \) is:
\[
Z = 20x + 30y
\]
### Step 3: Set Up the Constraints
1. **Time Constraint**: Product A takes \( \frac{1}{2} \) hours and product B takes 1 hour. The total production time cannot exceed 40 hours:
\[
\frac{1}{2}x + y \leq 40
\]
This can be rewritten as:
\[
x + 2y \leq 80
\]
2. **Turnover Constraint**: The total turnover must not be less than Rs. 10,000:
\[
200x + 300y \geq 10000
\]
This can be simplified to:
\[
2x + 3y \geq 100
\]
3. **Demand Constraints**: There is a permanent order for 14 units of product A and 16 units of product B:
\[
x \geq 14
\]
\[
y \geq 16
\]
4. **Non-negativity Constraints**:
\[
x \geq 0, \quad y \geq 0
\]
### Step 4: Graph the Constraints
To find the feasible region, we will graph the constraints on the coordinate plane.
1. **Constraint 1**: \( x + 2y \leq 80 \)
- When \( x = 0 \), \( y = 40 \) (point (0, 40))
- When \( y = 0 \), \( x = 80 \) (point (80, 0))
2. **Constraint 2**: \( 2x + 3y \geq 100 \)
- When \( x = 0 \), \( y = \frac{100}{3} \approx 33.33 \) (point (0, 33.33))
- When \( y = 0 \), \( x = 50 \) (point (50, 0))
3. **Demand Constraints**:
- \( x = 14 \) (vertical line)
- \( y = 16 \) (horizontal line)
### Step 5: Identify the Feasible Region
The feasible region is determined by the intersection of all the constraints. The vertices of this region will be calculated next.
### Step 6: Find the Intersection Points
1. **Intersection of \( x + 2y = 80 \) and \( 2x + 3y = 100 \)**:
- From \( x + 2y = 80 \), express \( x = 80 - 2y \).
- Substitute into \( 2(80 - 2y) + 3y = 100 \):
\[
160 - 4y + 3y = 100 \implies -y = -60 \implies y = 60
\]
- Substitute \( y = 60 \) back to find \( x \):
\[
x + 2(60) = 80 \implies x + 120 = 80 \implies x = -40 \quad \text{(not feasible)}
\]
2. **Intersection of \( x + 2y = 80 \) and \( y = 16 \)**:
\[
x + 2(16) = 80 \implies x + 32 = 80 \implies x = 48 \quad \text{(point (48, 16))}
\]
3. **Intersection of \( 2x + 3y = 100 \) and \( y = 16 \)**:
\[
2x + 3(16) = 100 \implies 2x + 48 = 100 \implies 2x = 52 \implies x = 26 \quad \text{(point (26, 16))}
\]
4. **Intersection of \( x = 14 \) and \( 2x + 3y = 100 \)**:
\[
2(14) + 3y = 100 \implies 28 + 3y = 100 \implies 3y = 72 \implies y = 24 \quad \text{(point (14, 24))}
\]
5. **Intersection of \( x = 14 \) and \( x + 2y = 80 \)**:
\[
14 + 2y = 80 \implies 2y = 66 \implies y = 33 \quad \text{(point (14, 33))}
\]
### Step 7: Evaluate the Objective Function at Each Vertex
Now we evaluate \( Z = 20x + 30y \) at each of the feasible points:
1. At (48, 16):
\[
Z = 20(48) + 30(16) = 960 + 480 = 1440
\]
2. At (26, 16):
\[
Z = 20(26) + 30(16) = 520 + 480 = 1000
\]
3. At (14, 24):
\[
Z = 20(14) + 30(24) = 280 + 720 = 1000
\]
4. At (14, 33):
\[
Z = 20(14) + 30(33) = 280 + 990 = 1270
\]
### Step 8: Determine the Maximum Profit
The maximum profit occurs at (48, 16) with a profit of Rs. 1440.
### Conclusion
To maximize profit, the manufacturer should produce:
- **48 units of product A**
- **16 units of product B**
### Maximum Profit
The maximum profit is **Rs. 1440**.
---
To solve the problem of maximizing profit for the manufacturer producing products A and B, we will follow these steps:
### Step 1: Define the Variables
Let:
- \( x \) = number of units produced of product A
- \( y \) = number of units produced of product B
### Step 2: Formulate the Objective Function
...
Similar Questions
Explore conceptually related problems
If the production cost of each of product P_(2) is Rs. 430 , then wha is the total production cost of P_(2) ?
If the ratio of the dot product of two vectors and cross product of same two vectors is sqrt3 , the two vectors make angle
A company sells two different products A and B. the two products are produced in a common production proce is which has a total capacity of 500 hours ofusing man power. It takes 5 hours to produce a unit of A and 3 hours to produce a unit of B. The demand in the market shows that the maximum number of units of a that can be sold is 70 and that of B is 125. Profit on each of unit a is 20 Rs and on B is 125. How many units of A and B should be produced to to maximise the profit.
The cost price of a product was Rs 150, and it was sold at a profit of 30%. What was the selling price of the product?
A earns Rs 80 per hour and works for 8 hours a day. B earns Rs 60 per hour and works for 6 hours a day . What is the ratio of per day wages of A and B ?
A earns Rs. 80 per hour and work for 8 hours a day. B. earns Rs. 60 per hour and works for 6 hours a day. What is the ratio of per day wages of a and B?
.Ramsells his product at a profit of 12% .If the S.P of the product is Rs 25500 .Find the costs of the product
If a worker takes 2/3 hour to make a toy.then he will make 12 toys in 8 hours.
A company sells two different products A and B. The two products are produced in a common production process and are sold in two different markets. The production process has a total capacity of 45000 man-hours. It takes 5 hours to produce a unit of A and 3 hours to produce a unit of B. The market has been surveyed and company officials feel that the maximum number of units of A that can be sold is 7000 ad that of B is 10,000. If the profit is Rs. 60 per unit for the product A and Rs. 40 per unit for the product B, how many units of each product should be sold to maximize profit? Formulate the problem as LPP.
Recommended Questions
- A manufactures makes two products, A and B. Product A sell at Rs. 200 ...
Text Solution
|
- A manufacturer produces two products A and B. Both the products are ...
Text Solution
|
- A manufactures makes two products, A and B. Product A sell at Rs. 200 ...
Text Solution
|
- एक कंपनी एक उत्पाद के दो नमूने A और B बनती है । नमूना A के प्रत्येक ...
Text Solution
|
- एक कम्पनी दो प्रकार के उत्पाद A तथा B बनाती है तथा A को 5 रुपये प्रति ...
Text Solution
|
- एक निर्माता दो सामान A और B बनाता है। सामान A, 200 रू0 प्रति इकाई की द...
Text Solution
|
- उत्पादन संबंधी समस्या: एक निर्माणकारी कंपनी एक उत्पाद के दो नमुने (प्र...
Text Solution
|
- एक निर्माता A और B दो प्रकार के उत्पाद बनाता है | उत्पाद A को ₹ 200 मे...
Text Solution
|
- एक कम्पनी दो प्रकार की वस्तुएँ A और B बनती है | दो विभागों assembling ...
Text Solution
|