Home
Class 8
MATHS
A can do a piece of work in 20 days whil...

A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will calculate the amount of work done by A and B, and then determine how long they worked together before B left. ### Step 1: Calculate the work rates of A and B - A can complete the work in 20 days, so A's work rate is: \[ \text{Work rate of A} = \frac{1}{20} \text{ (work per day)} \] - B can complete the work in 30 days, so B's work rate is: \[ \text{Work rate of B} = \frac{1}{30} \text{ (work per day)} \] ### Step 2: Calculate the combined work rate of A and B - When A and B work together, their combined work rate is: \[ \text{Combined work rate} = \frac{1}{20} + \frac{1}{30} \] - To add these fractions, find a common denominator. The least common multiple of 20 and 30 is 60: \[ \frac{1}{20} = \frac{3}{60}, \quad \frac{1}{30} = \frac{2}{60} \] - Therefore, the combined work rate is: \[ \text{Combined work rate} = \frac{3}{60} + \frac{2}{60} = \frac{5}{60} = \frac{1}{12} \text{ (work per day)} \] ### Step 3: Determine the total work done by A in 10 days - A completes the remaining work in 10 days. Since A's work rate is \(\frac{1}{20}\), the amount of work A does in 10 days is: \[ \text{Work done by A in 10 days} = 10 \times \frac{1}{20} = \frac{10}{20} = \frac{1}{2} \text{ of the total work} \] ### Step 4: Calculate the total work - If A completed \(\frac{1}{2}\) of the total work in 10 days, then the total work can be represented as: \[ \text{Total work} = 1 \text{ (whole work)} \] ### Step 5: Determine the work done before B leaves - Since A completed \(\frac{1}{2}\) of the work alone, the other half must have been completed by A and B together. Thus, the work done by A and B together is: \[ \text{Work done by A and B together} = 1 - \frac{1}{2} = \frac{1}{2} \] ### Step 6: Calculate the time they worked together - Let \(T\) be the number of days they worked together. The work done by A and B together in \(T\) days is: \[ T \times \frac{1}{12} = \frac{1}{2} \] - Solving for \(T\): \[ T = \frac{1/2}{1/12} = \frac{1}{2} \times \frac{12}{1} = 6 \text{ days} \] ### Final Answer - A and B worked together for **6 days**. ---
Doubtnut Promotions Banner Mobile Dark
|

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Essay Type Question|5 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-1)|33 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS (Very Short Answer Type Questions)|30 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 20 days, whereas B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.

Rajan can do a piece of work in 24 days while Amit can do it in 30 days. In how many days can they complete it they work together?

Knowledge Check

  • A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    A
    70 days
    B
    `42(3)/4` days
    C
    `27(1)/7`days
    D
    `17(1)/7` days
  • A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

    A
    10.5
    B
    8
    C
    8.4
    D
    9
  • A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

    A
    10.5
    B
    8
    C
    `28/3`
    D
    9
  • Similar Questions

    Explore conceptually related problems

    A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?

    A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

    A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

    A can do a piece of work in 10 days and B can dothe same piece of work in 20 days. They start the work together but after 5 days A leaves off. B will do the remaining piece of work in..