One man and 2 boys can do a piece of wor...

One man and 2 boys can do a piece of work in 12 days. The same work can also be done by 3 men and 1 boy in 6 days. How long it would take for one man alone to complete the work?

Text Solution

Verified by Experts

Let man be m
Let boy be b
`1m+2b=1/12-(1)`
`3m+b=1/6-(2)`
from equation 1 and 2
`5m=1/2-1/3=1/4`
`m=1/20`
1 man take 20 days to complete the work on time.
Promotional Banner

Similar Questions

Explore conceptually related problems

2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy to do it?

2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy to do it?

2 men and 7 boys can do a piece of work in 4 days.The same work is done in 3 days by 4 men and 4 boys.How long would it take one man and one boy to do it?

2 men and 7 boys can do a piece of work in 4 days. It is done by 4 men and 4 boys in 3 days. How long would it take for one man or one boy to do it ?

2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy alone to do it ?

3 men and 4 boys can do a piece of work in 14 days, while 4 men and 6 boys can do it in 10 days. How long would it take 1 boy to finish the work?

2 men and 5 boys can do a piece of work in 4 days, while 4 men and 4 boys can do it in 3 days. How long would it take one man alone to do it and how many days would it take one boy alone to do it ?

6 men and 8 boys can do a piece of work in 7 days, while 8 men and 12 boys do the same work in 5 days. How long would it take one boy to finish the same work?