A and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?

Text Solution

Verified by Experts

`A` and `B` can do a piece of work in `12` days
In day both can do
`A+B=1/12` part of the work ........(i)
`B` and `C` can do the work in `15` days
Therefore in `1` day both can do
`B+C=1/15` part............(ii)
`C` and `A` can do the same work in `20` days
In `1` days both can do
`A+C=1/20` part..............(iii)
Adding `2(A+B+C)=1/12+1/15+1/20`
Adding all , we get
`2(A+B+C)=(5+4+3)/60`
`2(A+B+C)=12/60`
`2(A+B+C)=1/5`
`(A+B+C)= 1/10` work
C completes work `= (A+B+C)-(A+B)`
`=1/10-1/12`
C completes the whole work in 60 days
Similarly,
`B+C=1/15`
`B+(1/60)=1/15`
`B= 1/15-1/60`
`B=1/20`
B completes work in 20 days
` A+B=1/12`
` A+1/20=1/12`
`A= 1/12-1/20`
`A= 1/30`
A completes work in 30 days.
Promotional Banner

Topper's Solved these Questions

  • SQUARES AND SQUARE ROOTS

    RD SHARMA|Exercise All Questions|183 Videos
  • UNDERSTANDING PHASE-II (QUADRILATERALS)

    RD SHARMA|Exercise All Questions|46 Videos

Similar Questions

Explore conceptually related problems

A and B can do piece of work in 12 days; B and C in 15days;C and A in 20 days.In how many days will they finish it together and separately ?

A and B can do a piece of work in 12 days, B and C in 15 days C and A in 20 days. In how many days can C alone do it ?

A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?

A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?

A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

RD SHARMA-TIME AND WORK-All Questions
  1. Together Chotu and Nitu plough a field in 4 days. Nitu alone takes of ...

    Text Solution

    |

  2. Kami, Karya and Kirti can together weave a carpet in 4 days. Kami by h...

    Text Solution

    |

  3. A and B can do piece of work in 12 days; B and C in 15 days; C and A i...

    Text Solution

    |

  4. A\ a n d\ Q together can do a piece of work in 10 days, Q\ a n d\ R ca...

    Text Solution

    |

  5. A can do a piece of work in 25 days and B can finish it in 20 days. Th...

    Text Solution

    |

  6. A and B can polish the floors of a building in 25 days. A alone can do...

    Text Solution

    |

  7. Suneeta can do 1/15 th of a piece of work in a day. Abha can do the sa...

    Text Solution

    |

  8. 5 men can complete a job in 8 days. How many days will it take if 12 m...

    Text Solution

    |

  9. Seema weaves 25 baskets in 35 days. In how many days will she weave 11...

    Text Solution

    |

  10. If 15 boys earn Rs.900 in 5 days, how much will 20 boys earn in 7 days...

    Text Solution

    |

  11. Spinning 3 hrs daily, Kanta can spin 1kg cotton balls in 12 days. Spin...

    Text Solution

    |

  12. Somari sweeps 600 m long railway platform in 2 1/2 hours. His wife Ima...

    Text Solution

    |

  13. A cistern can be filled by one tap in 4 hours and by another in 3 hour...

    Text Solution

    |

  14. Pipe A can fill a cistern in 1/6 hours and pipe B can fill it in 1/8 h...

    Text Solution

    |

  15. One sixth of a cistern is filled by pipe at the rate of 6 lit/h, 4/6th...

    Text Solution

    |

  16. A pipe can fill a cistern in 6 hours. Due to a leak in the bottom i...

    Text Solution

    |

  17. A tank can be filled by two taps A\ a n d\ B in 12 hours and 16 hours ...

    Text Solution

    |

  18. Rakesh can do piece of work in 20 days. How much work can be do in ...

    Text Solution

    |

  19. Rohan can paint 1/3 of a painting in 6 days. How many days will he tak...

    Text Solution

    |

  20. Anil can do a piece of work in 5 days and ankur in 4 days. How long wi...

    Text Solution

    |