If M1 men can do W1 work in D1 days work...

If M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day then

Promotional Banner

Similar Questions

Explore conceptually related problems

50 persons can do a work in 12 days, working 6 h per day. 60 persons can do the same work in 8 days, working x h per days.The value of x is

A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a day?

24 men can do a work in 14 days by working 6 hours a day. If’ the work is to be completed in 8 days by working to *7 hours per day how many men are required?

Working 8 hours a day, 12 men can do a work in 30 days. Working 4 hours a day, 18 men can do the work in 30 d a y s b. 40 d a y s c. 45 d a y s d. 50 d a y s

If 78 men can do a work in 140 days, in how many days will 42 men do the same work ?

18 men can construct 200 m long wall in 16 days working 9 hours per day. In how many days can 36men construct 500 m long wall working 6 hours per day?

If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?