8 men and 12 boys can finish a work in 1...

8 men and 12 boys can finish a work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.

Text Solution

Verified by Experts

Let one man alone can finish the work in `{x}` days and one boy alone can finish the work in` y `days.
In one day man can do `\frac{1}{{x}}` th work, then 8 man can do `\frac{8}{{x}}` th part of work. In one day man can do `\frac{1}{y}` th work, then `8 `man can do `\frac{12}{y}` th part of work. Given together they can finish in `10 `days
`\therefore \frac{8}{{x}}+\frac{12}{{y}}=\frac{1}{10}`
Again `6` man can do in one day `=\frac{6}{x}` parts of the work.
...
Promotional Banner

Similar Questions

Explore conceptually related problems

8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.

8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days.Find the time taken by one man alone and that by one boy alone to finish the work.

8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by a man alone and that by 1 boy alone to finish the work.

8 men and 12 boys can finish a piece of work in 5 days, while 6 men and 8 boys can finish it in 7 days. Find the time taken by 1 man along and that by 1 boy alone to finish the work.

4 girls and 6 boys can finish a work in 5 ays while 3 girls and 4 boys can finish it in 7 days. Find the time taken by one girl alone and that by one boy alone to finish the work

Formulate the following problems as a pair of equations and then find their solutions. 4 men and 6 women can finish a piece of work in 21 days while 10 men and 3 women can finish it in 14 days. Find the time taken by one man along and that by one woman along to finish the work.

4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish in 7 days. Find the time taken by 1 man alone and 1 boy alone to finish the piece of work.

4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days , then the time taken by one man alone is

2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.