If 40 men can finish a piece of work in ...

If 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we can use the concept of work done, which is based on the number of men and the number of days they work. Here's the step-by-step solution: ### Step 1: Understand the Work Done We know that 40 men can finish the work in 60 days. Therefore, the total work can be expressed in terms of man-days. **Total Work = Number of Men × Number of Days** Total Work = 40 men × 60 days = 2400 man-days ### Step 2: Set Up the Equation for 75 Men Now, we need to find out how many days (let's call it 'D') it will take for 75 men to complete the same amount of work. **Total Work = Number of Men × Number of Days** 2400 man-days = 75 men × D days ### Step 3: Solve for D Now we can rearrange the equation to solve for D: D = Total Work / Number of Men D = 2400 man-days / 75 men ### Step 4: Perform the Calculation Now we will perform the division: D = 2400 / 75 To simplify this calculation: 1. Divide both the numerator and the denominator by 15: - 2400 ÷ 15 = 160 - 75 ÷ 15 = 5 So now we have: D = 160 / 5 = 32 days ### Conclusion Therefore, 75 men will finish the same work in **32 days**. ---
Promotional Banner

Topper's Solved these Questions

  • RATION AND PROPORTION

    RS AGGARWAL|Exercise EXERCISE 8C|21 Videos
  • PROPERTIES OF TRIANGLES

    RS AGGARWAL|Exercise EXERCISE 15-D|18 Videos
  • RATIONAL NUMBERS

    RS AGGARWAL|Exercise TEST PAPER -(4)|17 Videos

Similar Questions

Explore conceptually related problems

7 men can complete a work in 52 days. In how many days will 13 men finish the same work.

If 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?

8 men can finish a piece of work in 15 hours.In how many hours can 20 men finish it?

30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?

If 4 men or 7 women can do a work in 60 days, then in how many days will 8 men and 7 women finish the same work?

2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days. In how many days will 20 women finish it?

2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days. In how many days will 20 women finish it?