Home
Class 8
MATHS
A can do a job in 16 days and B can do t...

A can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in

A

34 days

B

22 days

C

36 days

D

48 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will find out how long C alone can finish the job based on the work rates of A, B, and C. ### Step 1: Determine the work rates of A and B - A can complete the job in 16 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{16} \text{ (job per day)} \] - B can complete the job in 12 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1}{12} \text{ (job per day)} \] ### Step 2: Determine the combined work rate of A and B - To find the combined work rate of A and B, we add their individual work rates: \[ \text{Combined work rate of A and B} = \frac{1}{16} + \frac{1}{12} \] - To add these fractions, we need to find a common denominator. The least common multiple (LCM) of 16 and 12 is 48. - Convert \(\frac{1}{16}\) to have a denominator of 48: \[ \frac{1}{16} = \frac{3}{48} \] - Convert \(\frac{1}{12}\) to have a denominator of 48: \[ \frac{1}{12} = \frac{4}{48} \] - Now, add the two fractions: \[ \text{Combined work rate of A and B} = \frac{3}{48} + \frac{4}{48} = \frac{7}{48} \] ### Step 3: Determine the combined work rate of A, B, and C - A, B, and C together can finish the job in 6 days. Therefore, their combined work rate is: \[ \text{Combined work rate of A, B, and C} = \frac{1}{6} \] ### Step 4: Find C's work rate - We know the combined work rate of A, B, and C is equal to the combined work rate of A and B plus C's work rate: \[ \frac{1}{6} = \frac{7}{48} + \text{Work rate of C} \] - To find C's work rate, we can rearrange the equation: \[ \text{Work rate of C} = \frac{1}{6} - \frac{7}{48} \] - To perform this subtraction, we need a common denominator. The LCM of 6 and 48 is 48. - Convert \(\frac{1}{6}\) to have a denominator of 48: \[ \frac{1}{6} = \frac{8}{48} \] - Now, subtract: \[ \text{Work rate of C} = \frac{8}{48} - \frac{7}{48} = \frac{1}{48} \] ### Step 5: Determine how long C takes to finish the job alone - If C's work rate is \(\frac{1}{48}\) (job per day), then the time taken by C to finish the job alone is the reciprocal of the work rate: \[ \text{Time taken by C} = \frac{1}{\frac{1}{48}} = 48 \text{ days} \] ### Final Answer C alone can finish the job in **48 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    RS AGGARWAL|Exercise TEST PAPER -13|10 Videos
  • TIME AND WORK

    RS AGGARWAL|Exercise TEST PAPER -13 ( Fill in the blanks )|4 Videos
  • TIME AND WORK

    RS AGGARWAL|Exercise EXERCISE 13A|19 Videos
  • THREE - DIMENSIONAL FIGURES

    RS AGGARWAL|Exercise EXERCISE 19 B|5 Videos
  • VOLUME AND SURFACE AREA OF SOLIDS

    RS AGGARWAL|Exercise TEST PAPER -20|16 Videos

Similar Questions

Explore conceptually related problems

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With the help of C, they did the job in 4 days only Then C alone can do the job in:

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in 9 1/5d a y s b. 9 2/5d a y s c. 10 d a y s d. 9 3/5d a y s

A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?

A and B were assigned to do a job for an amount of 1200. A alone can do it in 15 days, while B can do it in 12 days. With the help of C, they can finish in 5 days. The share of amount that C earns is

A and B were assigned to do a job for an amount of 1,200. A alone can do it in 15 days, while B can do it in 12 days. With the help of C, they can finish in 5 days. The share of amount that C earns is

A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work? (A) 5 (B) 5 (D) 8 (C) 6

RS AGGARWAL-TIME AND WORK -EXERCISE 13B
  1. A alone can do a piece of work in 10 days and B alone can do it in 15 ...

    Text Solution

    |

  2. A man can do a piece of work in 5 days. He and his son working togethe...

    Text Solution

    |

  3. A can do a job in 16 days and B can do the same job in 12 days. With t...

    Text Solution

    |

  4. एक काम को ख़त्म करने में A , B की तुलना में 50 % समय अधिक लेता है...

    Text Solution

    |

  5. A works twice as fast as B. If both of them can together finish a piec...

    Text Solution

    |

  6. A alone can finish a piece of work in 10 days which B alone can do in ...

    Text Solution

    |

  7. The rates of working of A and B are in the ratio 3:4.The number of day...

    Text Solution

    |

  8. A and B together can do a piece of work in 12 days; B and C can do it ...

    Text Solution

    |

  9. 3 men or 5 women can do a work in 12 days. How long will 6 men and 5 w...

    Text Solution

    |

  10. A can do a piece of work in 15 days. B is 50% more efficient than A, B...

    Text Solution

    |

  11. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  12. A किसी काम को 20 दिनों में कर सकता हैजबकि बी उसी काम को 12 दिनों में क...

    Text Solution

    |

  13. A can do a piece of work in 25 days , which B alone can do in 20 days....

    Text Solution

    |

  14. दो पाइप A और B एक टैंक को क्रमश: 20 मिनट और 30 मिनट में भर सकते है । य...

    Text Solution

    |

  15. एक नल किसी टंकी को 8 घंटे में भर सकता है और दूसरा पाइप 16 घंटे में खाल...

    Text Solution

    |

  16. A pump can fill a tank in 2 hours. Due to a leak in the tank it takes ...

    Text Solution

    |

  17. A tank fills two taps A and B in 10 hours and 12 hours respectively, w...

    Text Solution

    |