A can do a piece ofwork in 14 days and B is 40% more efficient than A. In how many days can B finish it ?

A

10 days

B

`7(1)/(2)` days

C

`5(1)/(4)` days

D

`5(3)/(5)` days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    RS AGGARWAL|Exercise TEST PAPER -13 ( Fill in the blanks )|4 Videos
  • TIME AND WORK

    RS AGGARWAL|Exercise EXERCISE 13B|17 Videos
  • THREE - DIMENSIONAL FIGURES

    RS AGGARWAL|Exercise EXERCISE 19 B|5 Videos
  • VOLUME AND SURFACE AREA OF SOLIDS

    RS AGGARWAL|Exercise TEST PAPER -20|16 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?

A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

A and B can do a piece of work in 12 days. A is one and a half times more efficient than B. In how many days does A complete the work independently?