12 men and 18 boys, working `7 1/2` , hours a day, can do a piece of work in 60 day. If a man works equal to 2 boys, then how many boys will be required to help 21 men to do twice the work in 50 day, working 9 hours a day? `30` b. `42` c. `48` d. `90`

Promotional Banner

Similar Questions

Explore conceptually related problems

36 men can do a piece of work in 12 days. In how many days 9 men can do the same work?

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?

72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?

If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

24 men working at 8 hours per day can do a piece of work in 15 days. In how many days can 20 men working at 9 hours per day can complete the same work?

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?