2 men and 7 boys can do a piece of wo...

2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy to do it?

Text Solution

Verified by Experts

Let 1 man can do a piece of work in x days while a boy can do a piece of work in y ways.
`therefore` One man's one day work = `(1)/(x)`
and one boy's one day work = `(1)/(y)`
According to given conditions,
`(2)/(x) + (7)/(y) = (1)/(4) " ...(1)"`
and `(4)/(x) + (4)/(y) = (1)/(3) " ...(2)"`
Multiplying equation (1) by 2 and (2) by 1, we get
`(4)/(x) + (14)/(y) = (1)/(2)` ...(3)
`(4)/(x) + (4)/(y) = (1)/(3)` ...(4)
Subtracting equation (4) from (3), we get
`(14)/(y) - (4)/(y) = (1)/(2) - (1)/(3)`
`implies (10)/(y) = (1)/(6)`
implies y = 60
Substituting y = 60 in equation (1), we get
`(2)/(x) + (7)/(60) = (1)/(4) implies (2)/(x) = (1)/(4) - (7)/(60)`
implies `(2)/(x) = (8)/(60)`
implies 8x = 120 or x = 15
Hence, one man would do the work in 15 days and one boy in 60 days.
Promotional Banner

Topper's Solved these Questions

  • LINEAR EQUATIONS IN TWO VARIABLES

    NAGEEN PRAKASHAN|Exercise Exercise 3a|18 Videos
  • LINEAR EQUATIONS IN TWO VARIABLES

    NAGEEN PRAKASHAN|Exercise Exercise 3b|30 Videos
  • INTRODUCTION TO TRIGONOMETRY

    NAGEEN PRAKASHAN|Exercise Revision Exercise Long Answer Questions|5 Videos
  • POLYNOMIALS

    NAGEEN PRAKASHAN|Exercise Revision Exercise Long Answer Questions|4 Videos

Similar Questions

Explore conceptually related problems

One man and 2 boys can do a piece of work in 12 days.The same work can also be done by 3 men and 1 boy in 6days.How long it would take for one man alone to complete the work?

If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

12 men and 16 boys can do a piece of work in 5 days. 13 men and 24 boys can do the same work in 4 days. How long will 7 men and 10 boys take to do the same work?