40 men can complete a piece of work in 15 days. 20 more men join them after 5 days they start doing work. How many days will be required by them to finish the remaining work? a. `7 2/3\ d a y s` b. `6 1/5\ d a y s` c. `8 1/4\ d a y s` d. `6 2/3\ d a y s`

Promotional Banner

Similar Questions

Explore conceptually related problems

24 men can complete a piece of work in 15 days. 2 days after the 24 men started working, 4 men left the work. How many more days will the remaining men now take to complete the remaining work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

45 men can complete a work in 16 days.Six days after they started working,30 more men joined them.How many days will they now take to complete the remaining work?

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? 10 d a y s b. 12 d a y s c. 14 d a y s d. 16 d a y s e. none of these