Five workers take `"12"` days to weed a `` field.How many days would `"6` workers take ? How many would `15` take?

Promotional Banner

Similar Questions

Explore conceptually related problems

Five workers take 12 days to weed a field. How many days would 6 workers take ? How many days would 15 workers take ?

24 workers can build a wall in 15 days. How many days will 9 workers take to build a similar wall?

Four workers can build a house in 9 days. How many days would it takes 3 workers to build the same house?

If 24 workers can build a wall in 15 days, how many days will 8 workers take to build a similar wall?

12 worker take 4 hours to complete a job.How long would it take 15 workers to complete the job?