Rakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?

Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work ?

A can do a piece of work in 25 days and B can finish it in 20 days.They work together for 5 days and then A goes away.In how many days will B finish the remaining work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

Deepak can do a piece of work in 25 days and Ashok can do the same work in 40 days.They work together for 5days and then Deepak goes away.In how many days will Ashok finish the remaining work?