A can do a piece of work in 10 days and ...

A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in?

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A can do a piece of work in 10 days,B in 12 days and C in 15 days.All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished.How long did the work last?

RS AGGARWAL-TIME AND WORK-All Questions
  1. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  2. A can do a certain job in 12 days . B is 60% more efficient than A....

    Text Solution

    |

  3. A can do a piece of work in 10 days and B in 20 days. They begin toget...

    Text Solution

    |

  4. A can do a piece of work in 10 days , B in 12 days and C in 15 days.Al...

    Text Solution

    |

  5. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |

  6. A and B working separately can do a piece of work in 9 and 12 days ...

    Text Solution

    |

  7. A can do a piece of work in 120 days and B can do it in 150 days. The ...

    Text Solution

    |

  8. A and  B can do a piece of work in 12 days. B and C together can do ...

    Text Solution

    |

  9. 45 men can complete a work in 16 days. Six days after they started ...

    Text Solution

    |

  10. 10 persons begin to work together on a job but after some days 4 pe...

    Text Solution

    |

  11. 9 children can complete a piece of work in 360 days. 18 men can com...

    Text Solution

    |

  12. 2 men and 3 boys can do a piece of work in 10 days while 3 men and ...

    Text Solution

    |

  13. 3 men and 4 women can earn Rs. 3780 in 7 days. 11 men and 13 women ...

    Text Solution

    |

  14. Ayesha can complete a piece of work in 16 days. Amita can complete ...

    Text Solution

    |

  15. In a certain factory there are five workers A ,\ B ,\ C ,\ D and E ...

    Text Solution

    |

  16. A tyre has two punctures. The first puncture alone would have made the...

    Text Solution

    |

  17. A can knit a pair of socks in 3 days. B can knit the same pair in 9...

    Text Solution

    |

  18. A can complete a work in 6 days while B can complete the same work ...

    Text Solution

    |

  19. A can do a piece of work in 8 days and B can do the same piece of work...

    Text Solution

    |

  20. George takes 8 hours to copy a 50-page manuscript while Sonia can c...

    Text Solution

    |