Amit and Sumit can plough a field in 4 d...

Amit and Sumit can plough a field in 4 days. Sumit alone can plough the field in 6 days. In how many days will Amit alone plough the field? a. `10\ d a y s` b. `12\ d a y s` c. `15\ \ d a y s` d. `14\ d a y s`

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

Together Chotu and Nitu plough a field in 4 days.Nitu alone takes of 6 days to plough the same field.In how many days can Chotu alone plough the field?

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? 10 d a y s b. 12 d a y s c. 14 d a y s d. 16 d a y s e. none of these

A\ a n d\ B can polish the floors of a building in 10 days. A alone can do 1/4 of work in 12 days. In how many days can B alone polish the floor?

3 men or 6 women can do a piece of work in 20 days. In how many days will 12 men and 8 women do the same work? 3 1/2d a y s b. 3 3/4d a y s c. 4\ d a y s d. 5\ d a y s

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?

Working together, P, Q and R reap a field in 6 days . If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field ? A. 32 days B. 40 days C. 45 days D. 60 days

RS AGGARWAL-TIME AND WORK-All Questions
  1. Reena, Aastha and Shloka can independently complete a piece of work...

    Text Solution

    |

  2. A man can do a job in 15 days. His father takes 20 days and his son fi...

    Text Solution

    |

  3. Amit and Sumit can plough a field in 4 days. Sumit alone can plough th...

    Text Solution

    |

  4. Two spinning machines A and B can together produce 3,00,000 metres ...

    Text Solution

    |

  5. A can lay railway track between two given stations in 16 days and B...

    Text Solution

    |

  6. A can complete 1/3 of a work in 5 days and B, 2/5 of the work in 10 da...

    Text Solution

    |

  7. X can do 1/4 of a work in 10 days, Y can do 40% of the work in 40 days...

    Text Solution

    |

  8. A man and a boy together can do a certain amount of digging in 40 d...

    Text Solution

    |

  9. A takes twice as much time as B or thrice as much time as C to fini...

    Text Solution

    |

  10. Work done by A in one day is half of the work done by B in one day. Wo...

    Text Solution

    |

  11. Rosa can eat 32 rosogollas in one hour. Her sister Lila needs three ho...

    Text Solution

    |

  12. A conveyor belt delivers baggage at the rate of 3 tons in 5 minutes...

    Text Solution

    |

  13. A manufacturer builds a machine which will address 500 envelopes in ...

    Text Solution

    |

  14. Computer A takes 3 minutes to process an input while computer B tak...

    Text Solution

    |

  15. Bob and David are two typists. One afternoon, they were each given ...

    Text Solution

    |

  16. P, Q and R are three typists who working simultaneously can type 21...

    Text Solution

    |

  17. Ronald and Elan are working on an assignment. Ronald takes 6 hours to ...

    Text Solution

    |

  18. Cloth Makers Inc. has p spindles, each of which can produce q metres...

    Text Solution

    |

  19. Two workers A and B are engaged to do a piece of work.Working alone, A...

    Text Solution

    |

  20. Three friends Anne, Bob and Chris work together to do a certain hob....

    Text Solution

    |