A and B can do a work in 8 days, B and C...

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in `4\ d a y s` b. `6\ d a y s` c. `8\ d a y s` d. `12\ d a y s`

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in

A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in

A and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in

A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?

RS AGGARWAL-TIME AND WORK-All Questions
  1. A and B together can complete a work in 12 days, B and C together c...

    Text Solution

    |

  2. A can do a piece of work in 4 hours, B and C together in 3 hours, a...

    Text Solution

    |

  3. A and B can do a work in 8 days, B and C can do the same work in 12...

    Text Solution

    |

  4. A and B together can do a job in 2 days; B and C can 2 do it in 4 d...

    Text Solution

    |

  5. A and B can do a piece of work in 5 days; B and C can do it in 7 days;...

    Text Solution

    |

  6. A and B can do a piece of work in 12 days, B and C in 8 days and C and...

    Text Solution

    |

  7. Madhu takes twice as much time as Uma to complete a work and Rahul ...

    Text Solution

    |

  8. A takes 5 days more than B to do a certain job and 9 days more than...

    Text Solution

    |

  9. A works twice as fast as B. If B can complete a work in 12 days ind...

    Text Solution

    |

  10. A is twice as good a workman as B. If they work together, they can ...

    Text Solution

    |

  11. David and Michael together can finish a job in 4 days 19 hrs 12 min. I...

    Text Solution

    |

  12. A is thrice as good a workman as B and so takes 60 days less than B fo...

    Text Solution

    |

  13. A and B can do a job together in 7 days. A is 1 3/4 times as efficient...

    Text Solution

    |

  14. Kamal can do a work n 15 days. Bimal is 50% more efficient than Kam...

    Text Solution

    |

  15. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  16. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  17. A can do a piece of work in 10 days working 8 hours per day. If B i...

    Text Solution

    |

  18. A does half as much work as B in 3/4th of the time. If together they t...

    Text Solution

    |

  19. A is 50% as efficient as B.C does half of the work done by A and B ...

    Text Solution

    |

  20. Two workers A and B working together completed a job in 5 days. If ...

    Text Solution

    |