Kim can do a work in 3 days while David ...

Kim can do a work in 3 days while David can do the same work in 2 days. Both of them finish the work together and get Rs. 150. What is the share of Kim ? `R s .30` b. `R s .60` c. `R s .70` d. `R s .75`

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

A can do a work in 5 days while B can do the same work in 8 days. They worked together to complete the work and earned Rs. 6760. Find A's share ?

A can do a piece of work in 3 days while B can do the same work in 4 days. If they work together for a total wages of Rs. 2800, how much does A get?

A can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in

If A can do 1/4 of a work in 3 days and B can do 1/6 of the same work in 4 days, how much will A get if both work together and are paid Rs. 180 in all? a. R s .36 b. R s .60 c. R s .108 d. R s. 120

RS AGGARWAL-TIME AND WORK-All Questions
  1. A, B and C together earn Rs. 300 per day, while A and C together ea...

    Text Solution

    |

  2. A, B and C are employed to do a piece of work for Rs. 529. A and B tog...

    Text Solution

    |

  3. Kim can do a work in 3 days while David can do the same work in 2 da...

    Text Solution

    |

  4. If A can do 1/4 of a work in 3 days and B can do 1/6 of the same work ...

    Text Solution

    |

  5. A man and a boy received Rs. 800 as wages for 5 days for the work th...

    Text Solution

    |

  6. Two men undertake to do a piece of work for Rs. 1400. The first man...

    Text Solution

    |

  7. A sum of money is sufficient to pay A's wages for 21 days and B's w...

    Text Solution

    |

  8. A can do a piece of work in 10 days; B in 15 days. They work for 5 ...

    Text Solution

    |

  9. The daily wages of a worker are Rs. 100. Five workers can do a work...

    Text Solution

    |

  10. A and B together can complete a work in 12 days. A alone can comple...

    Text Solution

    |

  11. A,B and C completes a piece of work costing Rs. 1800. A worked for 6 d...

    Text Solution

    |

  12. A and B can complete a piece of work in 12 and 18 days respectively....

    Text Solution

    |

  13. A , B and C can do a piece of work in 11 days, 20 days and 55 days re...

    Text Solution

    |

  14. A, B and C can do a piece of work in 20, 30 and 60 days respectively. ...

    Text Solution

    |

  15. A can do a piece of work in 90 days, B in 40 days and C in 12 days. Th...

    Text Solution

    |

  16. A and B can finish a work, working on alternate days, in 19 days, when...

    Text Solution

    |

  17. A and B can separately do a piece of work in 20 and 15 days respective...

    Text Solution

    |

  18. A, B and C can do a piece of work in 36, 54 and 72 days respectively. ...

    Text Solution

    |

  19. Twenty women can do a work in sixteen days. Sixteen men can complete t...

    Text Solution

    |

  20. 10 men can complete a piece of work in 15 days and 15 women can comple...

    Text Solution

    |