If A can do 1/4 of a work in 3 days and ...

If A can do `1/4` of a work in 3 days and B can do `1/6` of the same work in 4 days, how much will A get if both work together and are paid Rs. 180 in all? a. `R s .36` b. `R s .60` c. `R s .108` d. `R s. 120`

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

If Ajit can do 1/4 of the work in 3 days and Sujit can 1/6 do of the same work in 4 days, how much will Ajit get if both work together and are paid ₹ 180 in all ?

A can do (1)/(5)th of a work in 4 days and B can do (1)/(6) th of the same work in 5 days. In how many days they can finish the work, if they work together?

A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

RS AGGARWAL-TIME AND WORK-All Questions
  1. A, B and C are employed to do a piece of work for Rs. 529. A and B tog...

    Text Solution

    |

  2. Kim can do a work in 3 days while David can do the same work in 2 da...

    Text Solution

    |

  3. If A can do 1/4 of a work in 3 days and B can do 1/6 of the same work ...

    Text Solution

    |

  4. A man and a boy received Rs. 800 as wages for 5 days for the work th...

    Text Solution

    |

  5. Two men undertake to do a piece of work for Rs. 1400. The first man...

    Text Solution

    |

  6. A sum of money is sufficient to pay A's wages for 21 days and B's w...

    Text Solution

    |

  7. A can do a piece of work in 10 days; B in 15 days. They work for 5 ...

    Text Solution

    |

  8. The daily wages of a worker are Rs. 100. Five workers can do a work...

    Text Solution

    |

  9. A and B together can complete a work in 12 days. A alone can comple...

    Text Solution

    |

  10. A,B and C completes a piece of work costing Rs. 1800. A worked for 6 d...

    Text Solution

    |

  11. A and B can complete a piece of work in 12 and 18 days respectively....

    Text Solution

    |

  12. A , B and C can do a piece of work in 11 days, 20 days and 55 days re...

    Text Solution

    |

  13. A, B and C can do a piece of work in 20, 30 and 60 days respectively. ...

    Text Solution

    |

  14. A can do a piece of work in 90 days, B in 40 days and C in 12 days. Th...

    Text Solution

    |

  15. A and B can finish a work, working on alternate days, in 19 days, when...

    Text Solution

    |

  16. A and B can separately do a piece of work in 20 and 15 days respective...

    Text Solution

    |

  17. A, B and C can do a piece of work in 36, 54 and 72 days respectively. ...

    Text Solution

    |

  18. Twenty women can do a work in sixteen days. Sixteen men can complete t...

    Text Solution

    |

  19. 10 men can complete a piece of work in 15 days and 15 women can comple...

    Text Solution

    |

  20. A job can be done by 3 skilled worksmen in 20 days or by 5 boys in 3...

    Text Solution

    |