A and B can complete a piece of work in ...

A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in a `14 1/3d a y s` b. `15 2/3d a y s` c. `16 1/3d a y s` d. `18 2/3d a y s`

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

A and B can complete a work in 12 days and 18 days, respectively. A begins to do the work and they work alternately one at a time for 1 day each. The whole work will be completed in how many days?

A and B can complete a work in 18 days and 15 days respectively. They started doing the work together but after 3 days A had to leave and B alone completed the remaining work. The whole work was completed in 9 3/4d a y s b. 10 1/4 d a y s c. 12 1/2d a y s d. 12 3/4d a y s

A\ a n d\ B can do a piece of work in 6 days and 4 days respectively. A started the work; worked at it for 2 days and then was joined by B . Find the total time taken to complete the work.

A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in

A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

RS AGGARWAL-TIME AND WORK-All Questions
  1. A and B together can complete a work in 12 days. A alone can comple...

    Text Solution

    |

  2. A,B and C completes a piece of work costing Rs. 1800. A worked for 6 d...

    Text Solution

    |

  3. A and B can complete a piece of work in 12 and 18 days respectively....

    Text Solution

    |

  4. A , B and C can do a piece of work in 11 days, 20 days and 55 days re...

    Text Solution

    |

  5. A, B and C can do a piece of work in 20, 30 and 60 days respectively. ...

    Text Solution

    |

  6. A can do a piece of work in 90 days, B in 40 days and C in 12 days. Th...

    Text Solution

    |

  7. A and B can finish a work, working on alternate days, in 19 days, when...

    Text Solution

    |

  8. A and B can separately do a piece of work in 20 and 15 days respective...

    Text Solution

    |

  9. A, B and C can do a piece of work in 36, 54 and 72 days respectively. ...

    Text Solution

    |

  10. Twenty women can do a work in sixteen days. Sixteen men can complete t...

    Text Solution

    |

  11. 10 men can complete a piece of work in 15 days and 15 women can comple...

    Text Solution

    |

  12. A job can be done by 3 skilled worksmen in 20 days or by 5 boys in 3...

    Text Solution

    |

  13. Five men are working to complete a work in 15 days. After five days ...

    Text Solution

    |

  14. A contractor undertakes to do a piece of work in 40 days. He engages...

    Text Solution

    |

  15. 16 men can finish a piece of work in 49 days. 14 men started workin...

    Text Solution

    |

  16. 7 men can complete a work in 12 day. They started the work and after...

    Text Solution

    |

  17. 12 men complete a work in 9 days. After they have worked for 6 days...

    Text Solution

    |

  18. Three men, four women and six children can complete a work in seven da...

    Text Solution

    |

  19. A man, a woman and a boy can complete a job in 3,4, and 12 days respec...

    Text Solution

    |

  20. 10 men and 15 women together can complete a work in 6 days. It take...

    Text Solution

    |