A, B and C can do a piece of work in 36,...

A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. `4` b. `8` c.`12` d. `24`

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A B and C can complete a piece of work in 24, 6 and 12 days respectively. They will complete the same work in :

A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.

A, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?

RS AGGARWAL-TIME AND WORK-All Questions
  1. A and B can finish a work, working on alternate days, in 19 days, when...

    Text Solution

    |

  2. A and B can separately do a piece of work in 20 and 15 days respective...

    Text Solution

    |

  3. A, B and C can do a piece of work in 36, 54 and 72 days respectively. ...

    Text Solution

    |

  4. Twenty women can do a work in sixteen days. Sixteen men can complete t...

    Text Solution

    |

  5. 10 men can complete a piece of work in 15 days and 15 women can comple...

    Text Solution

    |

  6. A job can be done by 3 skilled worksmen in 20 days or by 5 boys in 3...

    Text Solution

    |

  7. Five men are working to complete a work in 15 days. After five days ...

    Text Solution

    |

  8. A contractor undertakes to do a piece of work in 40 days. He engages...

    Text Solution

    |

  9. 16 men can finish a piece of work in 49 days. 14 men started workin...

    Text Solution

    |

  10. 7 men can complete a work in 12 day. They started the work and after...

    Text Solution

    |

  11. 12 men complete a work in 9 days. After they have worked for 6 days...

    Text Solution

    |

  12. Three men, four women and six children can complete a work in seven da...

    Text Solution

    |

  13. A man, a woman and a boy can complete a job in 3,4, and 12 days respec...

    Text Solution

    |

  14. 10 men and 15 women together can complete a work in 6 days. It take...

    Text Solution

    |

  15. A child can do a piece of work 15 hours slower than a woman. The chi...

    Text Solution

    |

  16. A group of workers having equal efficiency can complete a job in 4 ...

    Text Solution

    |

  17. A man, a woman and a boy can do a piece of work in 6, 9 and 18 days...

    Text Solution

    |

  18. If 3 men or 9 boys can finish a piece of work in 21 days, in how ma...

    Text Solution

    |

  19. 8 men can complete a piece of work in 20 days. 8 women can complete...

    Text Solution

    |

  20. 18 men can complete a piece of work in 63 days. 9 women take 189 da...

    Text Solution

    |