12 men complete a work in 9 days. After ...

12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work? `2\ d a y s` b. `\ 3\ d a y s` c. `4\ d a y s` d. `5d a y s` e. none of these

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

45 men can complete a work in 16 days.Six days after they started working,30 more men joined them.How many days will they now take to complete the remaining work?

12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? 10 d a y s b. 12 d a y s c. 14 d a y s d. 16 d a y s e. none of these

A piec of work can be done by 12 men in 24 days. After 4days. They started the work and then 6 more men joined them. How many days will they all take to complete the remaining work ?

RS AGGARWAL-TIME AND WORK-All Questions
  1. 16 men can finish a piece of work in 49 days. 14 men started workin...

    Text Solution

    |

  2. 7 men can complete a work in 12 day. They started the work and after...

    Text Solution

    |

  3. 12 men complete a work in 9 days. After they have worked for 6 days...

    Text Solution

    |

  4. Three men, four women and six children can complete a work in seven da...

    Text Solution

    |

  5. A man, a woman and a boy can complete a job in 3,4, and 12 days respec...

    Text Solution

    |

  6. 10 men and 15 women together can complete a work in 6 days. It take...

    Text Solution

    |

  7. A child can do a piece of work 15 hours slower than a woman. The chi...

    Text Solution

    |

  8. A group of workers having equal efficiency can complete a job in 4 ...

    Text Solution

    |

  9. A man, a woman and a boy can do a piece of work in 6, 9 and 18 days...

    Text Solution

    |

  10. If 3 men or 9 boys can finish a piece of work in 21 days, in how ma...

    Text Solution

    |

  11. 8 men can complete a piece of work in 20 days. 8 women can complete...

    Text Solution

    |

  12. 18 men can complete a piece of work in 63 days. 9 women take 189 da...

    Text Solution

    |

  13. 16 men can finish a work in 24 days and 48 boys can finish the same...

    Text Solution

    |

  14. 12 men can complete a piece of work in 4 days, while 15 women can comp...

    Text Solution

    |

  15. Twelve children take sixteen days to complete a work which can be c...

    Text Solution

    |

  16. Twenty-four men can complete a work in sixteen days.Thirty-two women c...

    Text Solution

    |

  17. 5 men and 2 boys working together can do four times as much work as...

    Text Solution

    |

  18. If 12 men and 16 boys can do a piece of work in 5 days; 13 men and ...

    Text Solution

    |

  19. 4 men and 6 women can complete a work in 8 days, While 3 men and 7 wom...

    Text Solution

    |

  20. 4 men and10 women were put on a work. They completed 1/3 of the wor...

    Text Solution

    |