40 men can complete a piece of work in 1...

40 men can complete a piece of work in 15 days. 20 more men join them after 5 days they start doing work. How many days will be required by them to finish the remaining work? a. `7 2/3\ d a y s` b. `6 1/5\ d a y s` c. `8 1/4\ d a y s` d. `6 2/3\ d a y s`

Promotional Banner

Topper's Solved these Questions

  • TIME AND DISTANCE

    RS AGGARWAL|Exercise All Questions|210 Videos
  • TRUE DISCOUNT

    RS AGGARWAL|Exercise All Questions|26 Videos

Similar Questions

Explore conceptually related problems

24 men can complete a piece of work in 15 days. 2 days after the 24 men started working, 4 men left the work. How many more days will the remaining men now take to complete the remaining work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

45 men can complete a work in 16 days.Six days after they started working,30 more men joined them.How many days will they now take to complete the remaining work?

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? 10 d a y s b. 12 d a y s c. 14 d a y s d. 16 d a y s e. none of these

RS AGGARWAL-TIME AND WORK-All Questions
  1. 8 men can complete a piece of work in 20 days. 8 women can complete...

    Text Solution

    |

  2. 18 men can complete a piece of work in 63 days. 9 women take 189 da...

    Text Solution

    |

  3. 16 men can finish a work in 24 days and 48 boys can finish the same...

    Text Solution

    |

  4. 12 men can complete a piece of work in 4 days, while 15 women can comp...

    Text Solution

    |

  5. Twelve children take sixteen days to complete a work which can be c...

    Text Solution

    |

  6. Twenty-four men can complete a work in sixteen days.Thirty-two women c...

    Text Solution

    |

  7. 5 men and 2 boys working together can do four times as much work as...

    Text Solution

    |

  8. If 12 men and 16 boys can do a piece of work in 5 days; 13 men and ...

    Text Solution

    |

  9. 4 men and 6 women can complete a work in 8 days, While 3 men and 7 wom...

    Text Solution

    |

  10. 4 men and10 women were put on a work. They completed 1/3 of the wor...

    Text Solution

    |

  11. one man , 3 woman and 4 boys can do a work in 96 hours . 2 man and 8 b...

    Text Solution

    |

  12. If 6 men and 8 boys can do a piece of work in 10 days while 26 men ...

    Text Solution

    |

  13. If 5 men and 3 women can reap 18 acre of crop in 4 days; 3 men and ...

    Text Solution

    |

  14. 25 men with 10 boys can do in 6 days as much work as 21 men with 30...

    Text Solution

    |

  15. 40 men can complete a piece of work in 15 days. 20 more men join the...

    Text Solution

    |

  16. 12 men can do a piece of work in 24 days. How many days are needed ...

    Text Solution

    |

  17. A can do in one day three times the work done by B in one day. They to...

    Text Solution

    |

  18. A, B and C can complete a piece of work in 24, 5 and 12 days respec...

    Text Solution

    |

  19. X can do a piece of work in 24 days. When he had worked for 4 days,...

    Text Solution

    |

  20. 6 men can complete a piece of work in 12 days, 8 women can complete...

    Text Solution

    |