A and B working together can do a piece...

A and B working together can do a piece of work in 12 days and A alone can caomplete the work in 18 days. How long will B alone take to complete the job?

Text Solution

AI Generated Solution

To solve the problem, we need to find out how long B alone will take to complete the work. Let's break it down step by step. ### Step 1: Determine the work done by A and B together A and B together can complete the work in 12 days. This means that in one day, they complete: \[ \text{Work done by A and B together in one day} = \frac{1}{12} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS|50 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 1|30 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?

A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?

A and B working together can do 30% of the work in 6 days. B alone can do the same work in 25 days. How long will A alone take to complete the same work?

A and B together can do a piece of work in 12 days and A alone can do it in 18 days. In how many days canBalone do it?

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

1 man and 1 woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days, can one woman alone complete the work?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 3
  1. A and B working together can do a piece of work in 12 days and A alo...

    Text Solution

    |

  2. Theere are 4 people whow can complete a work in 19 days. Individually...

    Text Solution

    |

  3. The ratio of the efficiency of P,Q and R is 2:3:5. The total wages of ...

    Text Solution

    |

  4. Amar, Bhavan and Chetan can make a total of 8 dosas in one minutes. Th...

    Text Solution

    |

  5. Eswar and Harish take 12 days and 16 days, respectively to complete a ...

    Text Solution

    |

  6. Pipes X,Y and Z are fitted to a tank. Each of Y and Z can fill the ta...

    Text Solution

    |

  7. X works four times as fast as Y.Y takes 60 days more than X to complet...

    Text Solution

    |

  8. One man and 7 women can complete a job in 16 days. 19 men and 10 women...

    Text Solution

    |

  9. M and N can complete a job in 18 days and 20 days, respectively. They ...

    Text Solution

    |

  10. Ganesh, Harish Sruesh and Mahesh worked together to produce 558 pieces...

    Text Solution

    |

  11. The efficiency of A, B and C is the same. They started working on a ce...

    Text Solution

    |

  12. 18 men and 36 women can level an area of 810 sq. in 6 days. The ratio ...

    Text Solution

    |

  13. There are 15 workers in groups in .Each can do 1 units per day. All th...

    Text Solution

    |

  14. Amar, Bhavan and Chetan can complete a job in 24 days, 36 days, and 48...

    Text Solution

    |

  15. Theere are 5 men in group. Each man can complete a job in 35 days. One...

    Text Solution

    |

  16. A job can be completed by 2 men, 3 women and 4 children in 15 days. Th...

    Text Solution

    |

  17. Mohan can complete a job in 8 days working 9 hourse a day. Sohan can c...

    Text Solution

    |

  18. Kiran and Pavanc an complete a job in 40 dasy and 50 daysm resepective...

    Text Solution

    |

  19. Pipes A,B and C are fitted to a tank .Each of A and B and can fill a t...

    Text Solution

    |

  20. P can complete a job in 60 days while Q can compelete in 90 days. With...

    Text Solution

    |

  21. Pipes X,Y and Z are fitted to a pank. X and Y can fill a tank in 18 ho...

    Text Solution

    |