The ratio of the efficientics of X.Y and...

The ratio of the efficientics of X.Y and Z is `:3:4:5`. The total amount of wates of X.Y and Z working for 20 days. 10 days and 12 days respectively was Rs. 6400. Find the amount of their total wages, if X,Y and Z worked for 30 days, 15 days, and 8 days respectively (in Rs.)

A

5700

B

9500

C

7600

D

8850

Text Solution

AI Generated Solution

To solve the problem step by step, we will follow the given information and calculate the required wages for X, Y, and Z. ### Step 1: Understand the efficiency ratio The efficiencies of X, Y, and Z are given in the ratio of 3:4:5. Let the efficiencies be: - Efficiency of X = 3k - Efficiency of Y = 4k ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS|50 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 1|30 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

The ratio of the efficiency of P,Q and R is 2:3:5 . The total wages of P,Q and R working for 14, 24 and 20 days, respectively are Rs. 6000. Find the total wages of three, if P works for 9 days, Q for 14 days and R for 8 days.

A and B can do a work in 20 days and 30 days respectively. A and B work on alternate days. Find the number of days to complete the work

A can do a piece of work in 6 days, B in 10 days and C in 15 days. They jointly complete the work and earn Rs 300. The sum of their wages for 2 days is

X,Y and Z can complete a job in 24 days, 32 days and 48 days respectively. They worked together and earned a total of ₹ x.Find the ratio of their shares.

X,Y and Z can complete a job in 24 days, 32 days and 48 days respectively. They worked together and earned a total of ₹ x.Find the ratio of their shares.

X and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………

X and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………

Ravi, Rohan and Rajesh alone can complete a work in 10, 12 and 15 days respectively. In how many days can the work be completed, if all three work together? A. 4 days B. 5 days C. 3 days D. 8 days

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 3
  1. The ratio of the efficientics of X.Y and Z is :3:4:5. The total amoun...

    Text Solution

    |

  2. Theere are 4 people whow can complete a work in 19 days. Individually...

    Text Solution

    |

  3. The ratio of the efficiency of P,Q and R is 2:3:5. The total wages of ...

    Text Solution

    |

  4. Amar, Bhavan and Chetan can make a total of 8 dosas in one minutes. Th...

    Text Solution

    |

  5. Eswar and Harish take 12 days and 16 days, respectively to complete a ...

    Text Solution

    |

  6. Pipes X,Y and Z are fitted to a tank. Each of Y and Z can fill the ta...

    Text Solution

    |

  7. X works four times as fast as Y.Y takes 60 days more than X to complet...

    Text Solution

    |

  8. One man and 7 women can complete a job in 16 days. 19 men and 10 women...

    Text Solution

    |

  9. M and N can complete a job in 18 days and 20 days, respectively. They ...

    Text Solution

    |

  10. Ganesh, Harish Sruesh and Mahesh worked together to produce 558 pieces...

    Text Solution

    |

  11. The efficiency of A, B and C is the same. They started working on a ce...

    Text Solution

    |

  12. 18 men and 36 women can level an area of 810 sq. in 6 days. The ratio ...

    Text Solution

    |

  13. There are 15 workers in groups in .Each can do 1 units per day. All th...

    Text Solution

    |

  14. Amar, Bhavan and Chetan can complete a job in 24 days, 36 days, and 48...

    Text Solution

    |

  15. Theere are 5 men in group. Each man can complete a job in 35 days. One...

    Text Solution

    |

  16. A job can be completed by 2 men, 3 women and 4 children in 15 days. Th...

    Text Solution

    |

  17. Mohan can complete a job in 8 days working 9 hourse a day. Sohan can c...

    Text Solution

    |

  18. Kiran and Pavanc an complete a job in 40 dasy and 50 daysm resepective...

    Text Solution

    |

  19. Pipes A,B and C are fitted to a tank .Each of A and B and can fill a t...

    Text Solution

    |

  20. P can complete a job in 60 days while Q can compelete in 90 days. With...

    Text Solution

    |

  21. Pipes X,Y and Z are fitted to a pank. X and Y can fill a tank in 18 ho...

    Text Solution

    |