12 men or 18 woman can do a work in 16 days. In how many days 12 men and 18 woman can do the work?

Text Solution

Verified by Experts

The correct Answer is:
8 days
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 1|30 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

If 12 men or 18 women can do a work in 14 days,then in how many days will 8 men and 16 women do the same work?

The ratio of work efficiency of a man and a woman is 3:2 . A woman can do a work in 30 days. In how many can 4 men and 4 women do the work?

If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

When 6 men and 8 women can do a piece of work in 15 days, then 11 men and 16 women can do the same work in 8 days. In how many days can 4 men and 4 women do the work ?

Six men and 4 women can do a piece of work in 32 days. Seven men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?

Six men and 4 women can do a piece of work in 32 days. Seven men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?

If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?

12 men and 15 women can do a work in 6 days, and 6 men and 12 women can do it in 10 days, in how many days can 8 men and 10 women do the same work?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-TEST YOUR CONCEPTS
  1. If A and B cadn do a work in x and y days, respectively, then time ta...

    Text Solution

    |

  2. A can do a task in 18 days. He works for 10 days and leaves. The remai...

    Text Solution

    |

  3. 12 men or 18 woman can do a work in 16 days. In how many days 12 men a...

    Text Solution

    |

  4. A, B and C can do a work in x,3x and 5x days, respectively. They worke...

    Text Solution

    |

  5. A and B can do a work in 20 and 30 days, respectiveyl .They completed ...

    Text Solution

    |

  6. A can point 6 walls in 5 days. B can point 8 walls (of the same area) ...

    Text Solution

    |

  7. The ratio of efficienciess of A, B can C is 2:3:4. Working together, t...

    Text Solution

    |

  8. On working 10 hourse a day, 15 men can complete a piece of work in 20 ...

    Text Solution

    |

  9. A and B can do a work in 20 days, B and C in 40 days and A and C in 3...

    Text Solution

    |

  10. A and B can finish a work together in 12 days, and B and C together in...

    Text Solution

    |

  11. Work done by (x+4) mean in (x+5) days is equal to the work done by (x...

    Text Solution

    |

  12. Pipe A in fill a tank in 15 horurs Pipe A and Pipe B together can fill...

    Text Solution

    |

  13. 18 men can construct 200 m long wall in 16 days working 9 hours per da...

    Text Solution

    |

  14. Vianay and Vikram can complete a work in 48 and 36 days, respectively ...

    Text Solution

    |

  15. A is twice as efficient as B. Time taken by B to complete (4)/(7) par...

    Text Solution

    |

  16. The ratio of work efficiency of a man and a woman is 3:2. A woman can ...

    Text Solution

    |

  17. 12 men of 15 women can do a work in 40 days. 8 men and 10 women can d...

    Text Solution

    |

  18. 12 men and 15 women can do a work in 6 days, and 6 men and 12 women ca...

    Text Solution

    |

  19. Certain sum is sufficient to pay wage to A for 15 days or to B for 30 ...

    Text Solution

    |

  20. A,B and C can do a work in 20,25 and 30, respectively. They together s...

    Text Solution

    |