Thirty men can dig a well in 10 days ...

Thirty men can dig a well in 10 days on working 8 hours a day. They started the work but after 2 days, 10 men left. How many hours a day should the remaining men work to complete it on time?

Text Solution

Verified by Experts

The correct Answer is:
12
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 1|30 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

27 men can dig a well in 20 days working 5 hours a day. They start digging it. After 4 days, 12 men leave. How hourse a day should the remaining men work to complete digging it by the scheduled date ?

10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?

24 men can complete a piece of work in 15 days. 2 days after the 24 men started working, 4 men left the work. How many more days will the remaining men now take to complete the remaining work?

Seven men can complete a work in 12 day. They started the work and after 5 days,two men left.In how many days will the work be completed by the remaining men? 5 b.backslash6 c.7 d.8 e.none of these

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.

Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?

A certain number of men can do a job in 10 days, working 6 hours a day. If the number of men is decreased by (1)/(3)rd , then in how many days can the remaining men complete the work, working 9 hours per day?

A certain number of men can do a job in 10 days, working 6 hours a day. If the number of men is decreased by (1)/(3)rd , then in how many days can the remaining men complete the work, working 9 hours per day?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-TEST YOUR CONCEPTS
  1. Certain sum is sufficient to pay wage to A for 15 days or to B for 30 ...

    Text Solution

    |

  2. A,B and C can do a work in 20,25 and 30, respectively. They together s...

    Text Solution

    |

  3. Anand is 50% more efficient than Bharath and Bharath is 100% more effi...

    Text Solution

    |

  4. 300 men can construct a200m long wall in 12 days working 8 hours a day...

    Text Solution

    |

  5. A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, ...

    Text Solution

    |

  6. Thirty men can dig a well in 10 days on working 8 hours a day. They...

    Text Solution

    |

  7. Time taken by A to complete a work is 7 days more than the time taken ...

    Text Solution

    |

  8. A is 20% more efficient than B.B can do a piece of work in 20 days. In...

    Text Solution

    |

  9. Three men or five women can complete a piece of work in 8 days. In how...

    Text Solution

    |

  10. A certain number of men completed a job in 10 days. If there 5 more me...

    Text Solution

    |

  11. Two pipes A and B can fill a tank in 20 and 24 minutes. Resepctively. ...

    Text Solution

    |

  12. a can complete a piece of work in 15 days. B can complete it in 10 day...

    Text Solution

    |

  13. Time taken by 8 men and 6 boys is 3 times the time taken 15 men and 30...

    Text Solution

    |

  14. Prakash, Rohit and Sameer cam complete a job in 1 days, 20 days, adn 1...

    Text Solution

    |

  15. Pipe A and pipe B can fill a tank in 24 minutes and 28 minutes , respe...

    Text Solution

    |

  16. In a group, there were M men. They sarted working on a job of 330 unit...

    Text Solution

    |

  17. Ram and Shyam can complete a job in 20 days. If they work together. If...

    Text Solution

    |

  18. A,B and C can complete a job in 20 days, 30 days, and 40 days, respect...

    Text Solution

    |

  19. 10 women can complete a job in 12 days . 4 of them started working on ...

    Text Solution

    |

  20. Prakash, Ramesh and Suresh started a job. After 2 days, Prakash left. ...

    Text Solution

    |