Home
Class 9
MATHS
A,B and C can complete a job in 20 days,...

A,B and C can complete a job in 20 days, 30 days, and 40 days, respectively. They worked for 6 days and then A left. B and C completed the job. Find B's wages in the total wages of Rs. 20,000 paid to them ( in Rs.)

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by A, B, and C, and then calculate B's share of the total wages. ### Step-by-Step Solution: 1. **Determine the work rates of A, B, and C:** - A can complete the job in 20 days, so A's work rate is \( \frac{1}{20} \) of the job per day. - B can complete the job in 30 days, so B's work rate is \( \frac{1}{30} \) of the job per day. - C can complete the job in 40 days, so C's work rate is \( \frac{1}{40} \) of the job per day. 2. **Calculate the combined work rate of A, B, and C:** \[ \text{Combined work rate} = \frac{1}{20} + \frac{1}{30} + \frac{1}{40} \] To add these fractions, we need a common denominator. The least common multiple of 20, 30, and 40 is 120. \[ \frac{1}{20} = \frac{6}{120}, \quad \frac{1}{30} = \frac{4}{120}, \quad \frac{1}{40} = \frac{3}{120} \] \[ \text{Combined work rate} = \frac{6 + 4 + 3}{120} = \frac{13}{120} \] 3. **Calculate the work done by A, B, and C in 6 days:** \[ \text{Work done in 6 days} = 6 \times \frac{13}{120} = \frac{78}{120} = \frac{13}{20} \] This means that after 6 days, \( \frac{13}{20} \) of the job is completed. 4. **Calculate the remaining work:** \[ \text{Remaining work} = 1 - \frac{13}{20} = \frac{7}{20} \] 5. **Determine the work rate of B and C together:** \[ \text{B's work rate} = \frac{1}{30}, \quad \text{C's work rate} = \frac{1}{40} \] \[ \text{Combined work rate of B and C} = \frac{1}{30} + \frac{1}{40} \] Using a common denominator of 120: \[ \frac{1}{30} = \frac{4}{120}, \quad \frac{1}{40} = \frac{3}{120} \] \[ \text{Combined work rate of B and C} = \frac{4 + 3}{120} = \frac{7}{120} \] 6. **Calculate the time taken by B and C to complete the remaining work:** Let \( x \) be the number of days B and C work together to finish the remaining work. \[ \text{Work done by B and C in } x \text{ days} = x \times \frac{7}{120} \] Setting this equal to the remaining work: \[ x \times \frac{7}{120} = \frac{7}{20} \] To solve for \( x \): \[ x = \frac{7}{20} \times \frac{120}{7} = 6 \text{ days} \] 7. **Total days worked by each person:** - A worked for 6 days. - B worked for \( 6 + 6 = 12 \) days. - C worked for \( 6 + 6 = 12 \) days. 8. **Calculate the total work done by each person:** - Work done by A: \[ 6 \times \frac{1}{20} = \frac{6}{20} = \frac{3}{10} \] - Work done by B: \[ 12 \times \frac{1}{30} = \frac{12}{30} = \frac{2}{5} = \frac{8}{20} \] - Work done by C: \[ 12 \times \frac{1}{40} = \frac{12}{40} = \frac{3}{10} \] 9. **Calculate the total work done:** \[ \text{Total work} = \frac{3}{10} + \frac{8}{20} + \frac{3}{10} = \frac{6}{20} + \frac{8}{20} + \frac{6}{20} = \frac{20}{20} = 1 \] 10. **Calculate the ratio of work done:** - A's share: \( \frac{3}{10} \) - B's share: \( \frac{8}{20} = \frac{2}{5} \) - C's share: \( \frac{3}{10} \) The ratio of work done by A, B, and C is: \[ 3:4:3 \] 11. **Calculate B's wages from the total wages of Rs. 20,000:** - Total parts = \( 3 + 4 + 3 = 10 \) - B's share = \( 4 \) parts \[ \text{B's wages} = \frac{4}{10} \times 20000 = 8000 \text{ Rs.} \] ### Final Answer: B's wages are Rs. 8,000.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 1|30 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

P,Q and R can complete a job in 6 days, 9 days and 12 days, respectively. They worked together and completed it. They earned a total of Rs. 2600. Find P's share ( in Rs.)

A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, respectively. They worked together and earned a total of Rs. 660. Find the B's share (in rupees)

M and N can complete a job in 18 days and 20 days, respectively. They worked on it on alternative days starting with M. Find the time taken to comlete it (in day)

A and B can do a work in 20 days and 30 days respectively. A and B work on alternate days. Find the number of days to complete the work

P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

P,Q and R can complete a job in 20 days, 30 and 40 days respectiely. They started working on it. Q and R left afte working for certain number of days and P alone completed the remaing work 7 days. Find the time taken to complete the job (in days)

PEARSON IIT JEE FOUNDATION- TIME AND WORK-TEST YOUR CONCEPTS
  1. Certain sum is sufficient to pay wage to A for 15 days or to B for 30 ...

    Text Solution

    |

  2. A,B and C can do a work in 20,25 and 30, respectively. They together s...

    Text Solution

    |

  3. Anand is 50% more efficient than Bharath and Bharath is 100% more effi...

    Text Solution

    |

  4. 300 men can construct a200m long wall in 12 days working 8 hours a day...

    Text Solution

    |

  5. A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, ...

    Text Solution

    |

  6. Thirty men can dig a well in 10 days on working 8 hours a day. They...

    Text Solution

    |

  7. Time taken by A to complete a work is 7 days more than the time taken ...

    Text Solution

    |

  8. A is 20% more efficient than B.B can do a piece of work in 20 days. In...

    Text Solution

    |

  9. Three men or five women can complete a piece of work in 8 days. In how...

    Text Solution

    |

  10. A certain number of men completed a job in 10 days. If there 5 more me...

    Text Solution

    |

  11. Two pipes A and B can fill a tank in 20 and 24 minutes. Resepctively. ...

    Text Solution

    |

  12. a can complete a piece of work in 15 days. B can complete it in 10 day...

    Text Solution

    |

  13. Time taken by 8 men and 6 boys is 3 times the time taken 15 men and 30...

    Text Solution

    |

  14. Prakash, Rohit and Sameer cam complete a job in 1 days, 20 days, adn 1...

    Text Solution

    |

  15. Pipe A and pipe B can fill a tank in 24 minutes and 28 minutes , respe...

    Text Solution

    |

  16. In a group, there were M men. They sarted working on a job of 330 unit...

    Text Solution

    |

  17. Ram and Shyam can complete a job in 20 days. If they work together. If...

    Text Solution

    |

  18. A,B and C can complete a job in 20 days, 30 days, and 40 days, respect...

    Text Solution

    |

  19. 10 women can complete a job in 12 days . 4 of them started working on ...

    Text Solution

    |

  20. Prakash, Ramesh and Suresh started a job. After 2 days, Prakash left. ...

    Text Solution

    |