MATHS
A, B and C do a piece of work in, 8,16 a...

A, B and C do a piece of work in, 8,16 and 24 days, respectively. They work together and earn Rs. 528. What is the share of B?

A

Rs. 144

B

Rs. 152

C

Rs. 176

D

Rs. 168

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine the share of B when A, B, and C work together. Here’s a step-by-step breakdown of the solution: ### Step 1: Calculate the work done by A, B, and C in one day. - A can complete the work in 8 days, so the work done by A in one day is: \[ \text{Work done by A in one day} = \frac{1}{8} \] - B can complete the work in 16 days, so the work done by B in one day is: \[ \text{Work done by B in one day} = \frac{1}{16} \] - C can complete the work in 24 days, so the work done by C in one day is: \[ \text{Work done by C in one day} = \frac{1}{24} \] ### Step 2: Calculate the total work done by A, B, and C together in one day. To find the total work done by A, B, and C together in one day, we add their individual contributions: \[ \text{Total work in one day} = \frac{1}{8} + \frac{1}{16} + \frac{1}{24} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 8, 16, and 24 is 48. Now, converting each fraction: \[ \frac{1}{8} = \frac{6}{48}, \quad \frac{1}{16} = \frac{3}{48}, \quad \frac{1}{24} = \frac{2}{48} \] Adding them together: \[ \text{Total work in one day} = \frac{6}{48} + \frac{3}{48} + \frac{2}{48} = \frac{11}{48} \] ### Step 3: Calculate the share of B based on the work done. The share of each person is proportional to the amount of work they do. B's share of the total work done in one day is: \[ \text{B's work} = \frac{1}{16} \] Now, we find the ratio of B's work to the total work done by A, B, and C together: \[ \text{Ratio of B's work} = \frac{\frac{1}{16}}{\frac{11}{48}} = \frac{48}{16 \times 11} = \frac{3}{11} \] ### Step 4: Calculate B's share of the total earnings. The total earnings for the work done is Rs. 528. B's share of the earnings can be calculated as follows: \[ \text{B's share} = \text{Total earnings} \times \text{Ratio of B's work} = 528 \times \frac{3}{11} \] Calculating B's share: \[ \text{B's share} = 528 \div 11 \times 3 = 48 \times 3 = 144 \] ### Final Answer: B's share of the earnings is Rs. 144. ---

To solve the problem, we need to determine the share of B when A, B, and C work together. Here’s a step-by-step breakdown of the solution: ### Step 1: Calculate the work done by A, B, and C in one day. - A can complete the work in 8 days, so the work done by A in one day is: \[ \text{Work done by A in one day} = \frac{1}{8} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS|50 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

A, B and C can do a work in x,3x and 5x days, respectively. They worked together and earned Rs. 460. What is the share of B?

A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, respectively. They worked together and earned a total of Rs. 660. Find the B's share (in rupees)

A, B and C can do a piece of work in 12 , 15 and 30 days respectively. If they do a work together, find the ratio in which the amount is to be distributed

A, B and C, working alone can do a piece of work in 12, 24 and 36 days respectively. They work together and get rs 3850 for completing the work. What is the difference in shares of B and C?

A,B anc C ,working alone can do a piece of work in 15,30 and 75 days respectively .They work together and get Rs. 1615 for completing the work .What is the difference in shares of A and C?

Amit, Vipul and Kapil can do a piece of work in 12, 16 and 24 days, respectively. If they complete the work together and get an amount of Rs. 2700, then what is the share of Vipul in that amount?

A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 1
  1. Certain men can do a piece of work in 22 days. If the number of men de...

    Text Solution

    |

  2. Pipe A can fill a tank in 20 minutes and pipe B can fill the tank in 3...

    Text Solution

    |

  3. A, B and C do a piece of work in, 8,16 and 24 days, respectively. They...

    Text Solution

    |

  4. A work three times as fast as B.B takes 56 days more than A to complet...

    Text Solution

    |

  5. A, B and C can complete a piece of work in 25, 30 and 50 days. Respect...

    Text Solution

    |

  6. When 6 men and 8 women can do a piece of work in 15 days, then 11 men ...

    Text Solution

    |

  7. A and B can do a piece of work in 12 days, B and C in 15 days and A a...

    Text Solution

    |

  8. P and Q can complete a certain in 28 days and 56 days, respectively. P...

    Text Solution

    |

  9. A piece of work in be done by 64 men in 17 days working for 9 hourse ...

    Text Solution

    |

  10. P and Q can do a piece of work in 12 days 16 days, resepetively. With ...

    Text Solution

    |

  11. A piece of work can be done by 9 men and 15 women in 24 days. In how m...

    Text Solution

    |

  12. A piec of work can be done by 12 men in 24 days. They started the wor...

    Text Solution

    |

  13. A and B can complete a piece of work in 4 days and 8 days, respctively...

    Text Solution

    |

  14. X and Y can do a piece of work in 4 days and 6 days resepectively. If ...

    Text Solution

    |

  15. Three marchines P,Q can do a piedce of work in 7,9 and 10 days, respec...

    Text Solution

    |

  16. A, B and C can complete a piece of work in 10 days, 20 days and 25 day...

    Text Solution

    |

  17. A group of 5 people can do a piece of work in certain number of of day...

    Text Solution

    |

  18. A and B can do a piece of work in 6 days and 9 days respectively, they...

    Text Solution

    |

  19. A, B and C can complete a piece of work in 27 days, 36 days, adn 45 da...

    Text Solution

    |

  20. If P can produce 60 cakes in 9 days and Q can product 70 cakes in 21 d...

    Text Solution

    |