Home
Class 9
MATHS
A, B and C can complete a piece of work ...

A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

A

14

B

12

C

18

D

10

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will determine how long it takes for A, B, and C to complete the work together and how long it takes for B to finish the remaining work after A and C leave. ### Step 1: Determine the work done by A, B, and C in one day. - A can complete the work in 25 days. Therefore, the work done by A in one day is: \[ \text{Work done by A in one day} = \frac{1}{25} \text{ of the work} \] - B can complete the work in 30 days. Therefore, the work done by B in one day is: \[ \text{Work done by B in one day} = \frac{1}{30} \text{ of the work} \] - C can complete the work in 50 days. Therefore, the work done by C in one day is: \[ \text{Work done by C in one day} = \frac{1}{50} \text{ of the work} \] ### Step 2: Calculate the total work done by A, B, and C in one day. To find the total work done by A, B, and C together in one day, we add their individual contributions: \[ \text{Total work done in one day} = \frac{1}{25} + \frac{1}{30} + \frac{1}{50} \] To add these fractions, we need to find a common denominator. The LCM of 25, 30, and 50 is 150. Now, convert each fraction: \[ \frac{1}{25} = \frac{6}{150}, \quad \frac{1}{30} = \frac{5}{150}, \quad \frac{1}{50} = \frac{3}{150} \] Adding these together: \[ \text{Total work done in one day} = \frac{6 + 5 + 3}{150} = \frac{14}{150} = \frac{7}{75} \] ### Step 3: Determine how many days they worked together before A and C left. Let \( x \) be the total number of days they worked together. Since A and C left 2 days before the work was completed, they worked together for \( x - 2 \) days. The total work done by A, B, and C in \( x - 2 \) days is: \[ \text{Work done} = \left(\frac{7}{75}\right)(x - 2) \] ### Step 4: Calculate the remaining work after A and C leave. After A and C leave, only B is left to complete the work. The work done by B in one day is \( \frac{1}{30} \). The total work done by B in 2 days is: \[ \text{Work done by B in 2 days} = 2 \times \frac{1}{30} = \frac{2}{30} = \frac{1}{15} \] ### Step 5: Set up the equation for total work. The total work is 1 (the whole job), so we can set up the equation: \[ \left(\frac{7}{75}\right)(x - 2) + \frac{1}{15} = 1 \] ### Step 6: Solve the equation. First, convert \( \frac{1}{15} \) to have a common denominator of 75: \[ \frac{1}{15} = \frac{5}{75} \] Now substitute back into the equation: \[ \left(\frac{7}{75}\right)(x - 2) + \frac{5}{75} = 1 \] Multiply through by 75 to eliminate the denominator: \[ 7(x - 2) + 5 = 75 \] \[ 7x - 14 + 5 = 75 \] \[ 7x - 9 = 75 \] \[ 7x = 84 \] \[ x = 12 \] ### Step 7: Conclusion The total time taken to complete the work is 12 days.

To solve the problem step by step, we will determine how long it takes for A, B, and C to complete the work together and how long it takes for B to finish the remaining work after A and C leave. ### Step 1: Determine the work done by A, B, and C in one day. - A can complete the work in 25 days. Therefore, the work done by A in one day is: \[ \text{Work done by A in one day} = \frac{1}{25} \text{ of the work} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS|50 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 1
  1. A, B and C do a piece of work in, 8,16 and 24 days, respectively. They...

    Text Solution

    |

  2. A work three times as fast as B.B takes 56 days more than A to complet...

    Text Solution

    |

  3. A, B and C can complete a piece of work in 25, 30 and 50 days. Respect...

    Text Solution

    |

  4. When 6 men and 8 women can do a piece of work in 15 days, then 11 men ...

    Text Solution

    |

  5. A and B can do a piece of work in 12 days, B and C in 15 days and A a...

    Text Solution

    |

  6. P and Q can complete a certain in 28 days and 56 days, respectively. P...

    Text Solution

    |

  7. A piece of work in be done by 64 men in 17 days working for 9 hourse ...

    Text Solution

    |

  8. P and Q can do a piece of work in 12 days 16 days, resepetively. With ...

    Text Solution

    |

  9. A piece of work can be done by 9 men and 15 women in 24 days. In how m...

    Text Solution

    |

  10. A piec of work can be done by 12 men in 24 days. They started the wor...

    Text Solution

    |

  11. A and B can complete a piece of work in 4 days and 8 days, respctively...

    Text Solution

    |

  12. X and Y can do a piece of work in 4 days and 6 days resepectively. If ...

    Text Solution

    |

  13. Three marchines P,Q can do a piedce of work in 7,9 and 10 days, respec...

    Text Solution

    |

  14. A, B and C can complete a piece of work in 10 days, 20 days and 25 day...

    Text Solution

    |

  15. A group of 5 people can do a piece of work in certain number of of day...

    Text Solution

    |

  16. A and B can do a piece of work in 6 days and 9 days respectively, they...

    Text Solution

    |

  17. A, B and C can complete a piece of work in 27 days, 36 days, adn 45 da...

    Text Solution

    |

  18. If P can produce 60 cakes in 9 days and Q can product 70 cakes in 21 d...

    Text Solution

    |

  19. 15 men and 25 men women can dig an area of 880 m^(2) in 8 days. In how...

    Text Solution

    |

  20. P and Q can do piece of work in 10 days in 10 days and 35 days. Respec...

    Text Solution

    |