Home
Class 9
MATHS
P and Q can complete a certain in 28 day...

P and Q can complete a certain in 28 days and 56 days, respectively. P works for 7 days, and then Q joins P . In how many more days, can they complete the work ?

A

7

B

14

C

21

D

28

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by P and Q, and then calculate how much work is left after P works alone for 7 days. Finally, we will find out how many more days they will take to complete the remaining work together. ### Step 1: Determine the work done by P and Q in one day. - P can complete the work in 28 days, so the work done by P in one day is: \[ \text{Work done by P in one day} = \frac{1}{28} \] - Q can complete the work in 56 days, so the work done by Q in one day is: \[ \text{Work done by Q in one day} = \frac{1}{56} \] ### Step 2: Calculate the total work done by P in 7 days. - In 7 days, P will complete: \[ \text{Work done by P in 7 days} = 7 \times \frac{1}{28} = \frac{7}{28} = \frac{1}{4} \] ### Step 3: Calculate the remaining work after P has worked for 7 days. - The total work can be considered as 1 unit (the whole work). Therefore, the remaining work after P has worked for 7 days is: \[ \text{Remaining work} = 1 - \frac{1}{4} = \frac{3}{4} \] ### Step 4: Calculate the combined work done by P and Q in one day. - The combined work done by P and Q in one day is: \[ \text{Combined work} = \frac{1}{28} + \frac{1}{56} \] To add these fractions, we need a common denominator. The least common multiple of 28 and 56 is 56. \[ \frac{1}{28} = \frac{2}{56} \] Therefore, \[ \text{Combined work} = \frac{2}{56} + \frac{1}{56} = \frac{3}{56} \] ### Step 5: Calculate how many days P and Q will take to complete the remaining work. - To find out how many days it will take for P and Q to complete the remaining \(\frac{3}{4}\) of the work, we set up the equation: \[ \text{Days required} = \frac{\text{Remaining work}}{\text{Combined work per day}} = \frac{\frac{3}{4}}{\frac{3}{56}} = \frac{3}{4} \times \frac{56}{3} = 14 \] ### Final Answer: - Therefore, P and Q will take **14 more days** to complete the work after Q joins P. ---

To solve the problem step by step, we will first determine the work done by P and Q, and then calculate how much work is left after P works alone for 7 days. Finally, we will find out how many more days they will take to complete the remaining work together. ### Step 1: Determine the work done by P and Q in one day. - P can complete the work in 28 days, so the work done by P in one day is: \[ \text{Work done by P in one day} = \frac{1}{28} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS|50 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?

P, Q and R can complete a work in 30 days, 15 days and 20 days respectively. P works on first day, then Q works on second day and then R works on third day and so on. In how many days the work will be completed?

Vianay and Vikram can complete a work in 48 and 36 days, respectively . If they work on alternate days beginning with Vinay, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 1
  1. A work three times as fast as B.B takes 56 days more than A to complet...

    Text Solution

    |

  2. A, B and C can complete a piece of work in 25, 30 and 50 days. Respect...

    Text Solution

    |

  3. When 6 men and 8 women can do a piece of work in 15 days, then 11 men ...

    Text Solution

    |

  4. A and B can do a piece of work in 12 days, B and C in 15 days and A a...

    Text Solution

    |

  5. P and Q can complete a certain in 28 days and 56 days, respectively. P...

    Text Solution

    |

  6. A piece of work in be done by 64 men in 17 days working for 9 hourse ...

    Text Solution

    |

  7. P and Q can do a piece of work in 12 days 16 days, resepetively. With ...

    Text Solution

    |

  8. A piece of work can be done by 9 men and 15 women in 24 days. In how m...

    Text Solution

    |

  9. A piec of work can be done by 12 men in 24 days. They started the wor...

    Text Solution

    |

  10. A and B can complete a piece of work in 4 days and 8 days, respctively...

    Text Solution

    |

  11. X and Y can do a piece of work in 4 days and 6 days resepectively. If ...

    Text Solution

    |

  12. Three marchines P,Q can do a piedce of work in 7,9 and 10 days, respec...

    Text Solution

    |

  13. A, B and C can complete a piece of work in 10 days, 20 days and 25 day...

    Text Solution

    |

  14. A group of 5 people can do a piece of work in certain number of of day...

    Text Solution

    |

  15. A and B can do a piece of work in 6 days and 9 days respectively, they...

    Text Solution

    |

  16. A, B and C can complete a piece of work in 27 days, 36 days, adn 45 da...

    Text Solution

    |

  17. If P can produce 60 cakes in 9 days and Q can product 70 cakes in 21 d...

    Text Solution

    |

  18. 15 men and 25 men women can dig an area of 880 m^(2) in 8 days. In how...

    Text Solution

    |

  19. P and Q can do piece of work in 10 days in 10 days and 35 days. Respec...

    Text Solution

    |

  20. Ram , Shaym and Tarun are three people on a job. Each takes m times th...

    Text Solution

    |