Three marchines P,Q can do a piedce of w...

Three marchines P,Q can do a piedce of work in 7,9 and 10 days, respectively. Deu to problem in P and Q, they are working only ay 70% and 90% of their effiency, resepectively. In how many days can P,Q and R together do the work ?

A

`1(2)/(3)` days

B

`2(1)/(3)` days

C

`2(3)/(2)` days

D

`3(1)/(3)` days

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS|50 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

A and B can do piece of work in 9 days and 18 days , respectively. As they were ill , they could do 90% and 72% of their efficiency respectively . How many days will they take to complete the work together?

A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?

A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 1
  1. A work three times as fast as B.B takes 56 days more than A to complet...

    Text Solution

    |

  2. A, B and C can complete a piece of work in 25, 30 and 50 days. Respect...

    Text Solution

    |

  3. When 6 men and 8 women can do a piece of work in 15 days, then 11 men ...

    Text Solution

    |

  4. A and B can do a piece of work in 12 days, B and C in 15 days and A a...

    Text Solution

    |

  5. P and Q can complete a certain in 28 days and 56 days, respectively. P...

    Text Solution

    |

  6. A piece of work in be done by 64 men in 17 days working for 9 hourse ...

    Text Solution

    |

  7. P and Q can do a piece of work in 12 days 16 days, resepetively. With ...

    Text Solution

    |

  8. A piece of work can be done by 9 men and 15 women in 24 days. In how m...

    Text Solution

    |

  9. A piec of work can be done by 12 men in 24 days. They started the wor...

    Text Solution

    |

  10. A and B can complete a piece of work in 4 days and 8 days, respctively...

    Text Solution

    |

  11. X and Y can do a piece of work in 4 days and 6 days resepectively. If ...

    Text Solution

    |

  12. Three marchines P,Q can do a piedce of work in 7,9 and 10 days, respec...

    Text Solution

    |

  13. A, B and C can complete a piece of work in 10 days, 20 days and 25 day...

    Text Solution

    |

  14. A group of 5 people can do a piece of work in certain number of of day...

    Text Solution

    |

  15. A and B can do a piece of work in 6 days and 9 days respectively, they...

    Text Solution

    |

  16. A, B and C can complete a piece of work in 27 days, 36 days, adn 45 da...

    Text Solution

    |

  17. If P can produce 60 cakes in 9 days and Q can product 70 cakes in 21 d...

    Text Solution

    |

  18. 15 men and 25 men women can dig an area of 880 m^(2) in 8 days. In how...

    Text Solution

    |

  19. P and Q can do piece of work in 10 days in 10 days and 35 days. Respec...

    Text Solution

    |

  20. Ram , Shaym and Tarun are three people on a job. Each takes m times th...

    Text Solution

    |