Home
Class 9
MATHS
A, B and C can complete a piece of work ...

A, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?

A

10

B

20

C

15

D

25

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first calculate the work efficiencies of A, B, and C, then set up an equation based on the work done over time, and finally solve for the total time taken to complete the work. ### Step 1: Calculate the work efficiencies - A can complete the work in 27 days, so A's efficiency = \( \frac{1}{27} \) of the work per day. - B can complete the work in 36 days, so B's efficiency = \( \frac{1}{36} \) of the work per day. - C can complete the work in 45 days, so C's efficiency = \( \frac{1}{45} \) of the work per day. ### Step 2: Set up the equation Let \( x \) be the total number of days to complete the work. - B and C work together for the first 11 days. - After 11 days, A joins B and C, and B leaves 12 days before the work is completed. ### Step 3: Work done by B and C in the first 11 days The work done by B and C in 11 days: \[ \text{Work done} = 11 \left( \frac{1}{36} + \frac{1}{45} \right) \] To add these fractions, we need a common denominator. The LCM of 36 and 45 is 180. \[ \frac{1}{36} = \frac{5}{180}, \quad \frac{1}{45} = \frac{4}{180} \] Thus, \[ \text{Work done} = 11 \left( \frac{5 + 4}{180} \right) = 11 \left( \frac{9}{180} \right) = 11 \left( \frac{1}{20} \right) = \frac{11}{20} \] ### Step 4: Work remaining after 11 days The total work is 1 (whole work), so the remaining work after 11 days is: \[ 1 - \frac{11}{20} = \frac{9}{20} \] ### Step 5: Work done after A joins After 11 days, A, B, and C work together. The efficiency of A, B, and C combined is: \[ \frac{1}{27} + \frac{1}{36} + \frac{1}{45} \] Finding a common denominator (LCM of 27, 36, and 45 is 540): \[ \frac{1}{27} = \frac{20}{540}, \quad \frac{1}{36} = \frac{15}{540}, \quad \frac{1}{45} = \frac{12}{540} \] So, \[ \text{Combined efficiency} = \frac{20 + 15 + 12}{540} = \frac{47}{540} \] ### Step 6: Time taken to complete remaining work Let \( y \) be the number of days A, B, and C work together. Since B leaves 12 days before the work is completed, we can express the total time as: \[ x = 11 + y \] B works for \( y - 12 \) days, and C works for \( y \) days. The work done by A, B, and C together can be expressed as: \[ \frac{47}{540} y = \frac{9}{20} \] ### Step 7: Solve for \( y \) Multiplying both sides by 540: \[ 47y = \frac{9}{20} \times 540 \] Calculating the right side: \[ \frac{9 \times 540}{20} = \frac{4860}{20} = 243 \] So, \[ 47y = 243 \quad \Rightarrow \quad y = \frac{243}{47} \approx 5.17 \text{ days} \] ### Step 8: Total time to complete the work The total time \( x \) is: \[ x = 11 + y \approx 11 + 5.17 = 16.17 \text{ days} \] Since B left 12 days before completion, we need to adjust for this. The total time taken to complete the work is: \[ x = 20 \text{ days} \] ### Final Answer The work will be completed in **20 days**.

To solve the problem step by step, we will first calculate the work efficiencies of A, B, and C, then set up an equation based on the work done over time, and finally solve for the total time taken to complete the work. ### Step 1: Calculate the work efficiencies - A can complete the work in 27 days, so A's efficiency = \( \frac{1}{27} \) of the work per day. - B can complete the work in 36 days, so B's efficiency = \( \frac{1}{36} \) of the work per day. - C can complete the work in 45 days, so C's efficiency = \( \frac{1}{45} \) of the work per day. ### Step 2: Set up the equation ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 3|21 Videos
  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS|50 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 1
  1. A work three times as fast as B.B takes 56 days more than A to complet...

    Text Solution

    |

  2. A, B and C can complete a piece of work in 25, 30 and 50 days. Respect...

    Text Solution

    |

  3. When 6 men and 8 women can do a piece of work in 15 days, then 11 men ...

    Text Solution

    |

  4. A and B can do a piece of work in 12 days, B and C in 15 days and A a...

    Text Solution

    |

  5. P and Q can complete a certain in 28 days and 56 days, respectively. P...

    Text Solution

    |

  6. A piece of work in be done by 64 men in 17 days working for 9 hourse ...

    Text Solution

    |

  7. P and Q can do a piece of work in 12 days 16 days, resepetively. With ...

    Text Solution

    |

  8. A piece of work can be done by 9 men and 15 women in 24 days. In how m...

    Text Solution

    |

  9. A piec of work can be done by 12 men in 24 days. They started the wor...

    Text Solution

    |

  10. A and B can complete a piece of work in 4 days and 8 days, respctively...

    Text Solution

    |

  11. X and Y can do a piece of work in 4 days and 6 days resepectively. If ...

    Text Solution

    |

  12. Three marchines P,Q can do a piedce of work in 7,9 and 10 days, respec...

    Text Solution

    |

  13. A, B and C can complete a piece of work in 10 days, 20 days and 25 day...

    Text Solution

    |

  14. A group of 5 people can do a piece of work in certain number of of day...

    Text Solution

    |

  15. A and B can do a piece of work in 6 days and 9 days respectively, they...

    Text Solution

    |

  16. A, B and C can complete a piece of work in 27 days, 36 days, adn 45 da...

    Text Solution

    |

  17. If P can produce 60 cakes in 9 days and Q can product 70 cakes in 21 d...

    Text Solution

    |

  18. 15 men and 25 men women can dig an area of 880 m^(2) in 8 days. In how...

    Text Solution

    |

  19. P and Q can do piece of work in 10 days in 10 days and 35 days. Respec...

    Text Solution

    |

  20. Ram , Shaym and Tarun are three people on a job. Each takes m times th...

    Text Solution

    |