The efficiency of A, B and C is the same...

The efficiency of A, B and C is the same. They started working on a certain job. After 5 days a leaves, after 5 moere days B leaves and C completes the remaining work in 5 more days. Find the time taken by eahc of them alone to complete the job. (in days)?

A

20

B

30

C

40

D

45

Text Solution

Verified by Experts

The correct Answer is:
B

Let us assume that each of A, B and C alone can do in x-axis 15 days
A works for 5 days, B works for 10 days and C works 15 days.
`:. (5)/(x)+(10)/(x)+(15)/(x)=1`
`(30)/(x)=1rArr=30`
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

P,Q and R can complete a job in 20 days, 30 and 40 days respectiely. They started working on it. Q and R left afte working for certain number of days and P alone completed the remaing work 7 days. Find the time taken to complete the job (in days)

Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:

A can complete a work in 15 days, B in 18 days. Find the time taken by them: if A leaves two days before the scheduled completion of the work.

A can complete a work in 12 days, B in 15 days. Find the time taken by them: if A leaves two days before the actual completion of the work.

A can complete a work in 12 days, B in 15 days. Find the time taken by them: if B leaves two days before the scheduled completion of the work.

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 3
  1. The ratio of the efficiency of P,Q and R is 2:3:5. The total wages of ...

    Text Solution

    |

  2. Amar, Bhavan and Chetan can make a total of 8 dosas in one minutes. Th...

    Text Solution

    |

  3. Eswar and Harish take 12 days and 16 days, respectively to complete a ...

    Text Solution

    |

  4. Pipes X,Y and Z are fitted to a tank. Each of Y and Z can fill the ta...

    Text Solution

    |

  5. X works four times as fast as Y.Y takes 60 days more than X to complet...

    Text Solution

    |

  6. One man and 7 women can complete a job in 16 days. 19 men and 10 women...

    Text Solution

    |

  7. M and N can complete a job in 18 days and 20 days, respectively. They ...

    Text Solution

    |

  8. Ganesh, Harish Sruesh and Mahesh worked together to produce 558 pieces...

    Text Solution

    |

  9. The efficiency of A, B and C is the same. They started working on a ce...

    Text Solution

    |

  10. 18 men and 36 women can level an area of 810 sq. in 6 days. The ratio ...

    Text Solution

    |

  11. There are 15 workers in groups in .Each can do 1 units per day. All th...

    Text Solution

    |

  12. Amar, Bhavan and Chetan can complete a job in 24 days, 36 days, and 48...

    Text Solution

    |

  13. Theere are 5 men in group. Each man can complete a job in 35 days. One...

    Text Solution

    |

  14. A job can be completed by 2 men, 3 women and 4 children in 15 days. Th...

    Text Solution

    |

  15. Mohan can complete a job in 8 days working 9 hourse a day. Sohan can c...

    Text Solution

    |

  16. Kiran and Pavanc an complete a job in 40 dasy and 50 daysm resepective...

    Text Solution

    |

  17. Pipes A,B and C are fitted to a tank .Each of A and B and can fill a t...

    Text Solution

    |

  18. P can complete a job in 60 days while Q can compelete in 90 days. With...

    Text Solution

    |

  19. Pipes X,Y and Z are fitted to a pank. X and Y can fill a tank in 18 ho...

    Text Solution

    |

  20. P,Q and R can complete a job in 6 days, 9 days and 12 days, respective...

    Text Solution

    |