18 men and 36 women can level an area of...

18 men and 36 women can level an area of 810 sq. in 6 days. The ratio of the areas that each man and each woman can level in the same amount of time is `3:1`. Find the number of dayss is which 22 men adn 14 women can level an area of 120 sq. m.

A

8

B

12

C

9

D

10

Text Solution

Verified by Experts

The correct Answer is:
D

Let the areas that each man and each woman can level (in sq. m.) b m/day and q/day respectively.
Area that 18 men and 36 women can level each day `=(18m+36w)` sq.m.
`:. 6(18m+36w)=810`
`18m+36w=135`
Given : `(m)/(w)=(3)/(1), i.e.,m=3w`
`:. 18(3w)+36w=135`
`90w-135`
`w=(3)/(2)`
`:. m=(9)/(2)`
Let the required number of days be d
`d(22m+14w)=1200`
`d(22((9)/(2))+14((3)/(2)))=1200`
`rArr120 d=122 rArrd=10`
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    PEARSON IIT JEE FOUNDATION|Exercise LEVEL 2|19 Videos
  • BANKING AND COMPUTING

    PEARSON IIT JEE FOUNDATION|Exercise Level 3|6 Videos

Similar Questions

Explore conceptually related problems

24 men can do work in X days and 32 women can do the same work in (X+8) days. The ratio of work done by 15 men and 12 women in the same time is 3 : 1 . What is the value of X ?

2 men and 3 women can do a piece of work in 16 days . In how many days can 4 men and 6 women do the same work?

If 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.

Five men or ten women can complete a job in 20 days. Find the time in which four men and four women can complete it (in days)

If 3 men or 5 women can solve a problem in 3 days then in how many days can 1 man and 2 women's solve the same problem

6 men or 10 women can reap a field in 15 days,then the number of days that 12 men and 5 women will take to reap the same field is

2 men and 3 women can do a piece of work in 10 days, while 3 men nd 2 women can do the same work in 8 days. Then, 2 men and 1 woman can do the same work in

PEARSON IIT JEE FOUNDATION- TIME AND WORK-LEVEL 3
  1. The ratio of the efficiency of P,Q and R is 2:3:5. The total wages of ...

    Text Solution

    |

  2. Amar, Bhavan and Chetan can make a total of 8 dosas in one minutes. Th...

    Text Solution

    |

  3. Eswar and Harish take 12 days and 16 days, respectively to complete a ...

    Text Solution

    |

  4. Pipes X,Y and Z are fitted to a tank. Each of Y and Z can fill the ta...

    Text Solution

    |

  5. X works four times as fast as Y.Y takes 60 days more than X to complet...

    Text Solution

    |

  6. One man and 7 women can complete a job in 16 days. 19 men and 10 women...

    Text Solution

    |

  7. M and N can complete a job in 18 days and 20 days, respectively. They ...

    Text Solution

    |

  8. Ganesh, Harish Sruesh and Mahesh worked together to produce 558 pieces...

    Text Solution

    |

  9. The efficiency of A, B and C is the same. They started working on a ce...

    Text Solution

    |

  10. 18 men and 36 women can level an area of 810 sq. in 6 days. The ratio ...

    Text Solution

    |

  11. There are 15 workers in groups in .Each can do 1 units per day. All th...

    Text Solution

    |

  12. Amar, Bhavan and Chetan can complete a job in 24 days, 36 days, and 48...

    Text Solution

    |

  13. Theere are 5 men in group. Each man can complete a job in 35 days. One...

    Text Solution

    |

  14. A job can be completed by 2 men, 3 women and 4 children in 15 days. Th...

    Text Solution

    |

  15. Mohan can complete a job in 8 days working 9 hourse a day. Sohan can c...

    Text Solution

    |

  16. Kiran and Pavanc an complete a job in 40 dasy and 50 daysm resepective...

    Text Solution

    |

  17. Pipes A,B and C are fitted to a tank .Each of A and B and can fill a t...

    Text Solution

    |

  18. P can complete a job in 60 days while Q can compelete in 90 days. With...

    Text Solution

    |

  19. Pipes X,Y and Z are fitted to a pank. X and Y can fill a tank in 18 ho...

    Text Solution

    |

  20. P,Q and R can complete a job in 6 days, 9 days and 12 days, respective...

    Text Solution

    |