Sunil can do a piece of work in 2 days w...

Sunil can do a piece of work in 2 days whileSaurav can do it in 3 days. They work together for a dayand rest of the work is done by Sachin in 1 day. If they get 1800 for the whole work, the wage of Sachin is

Promotional Banner

Similar Questions

Explore conceptually related problems

Sunil can do a piece of work in 2 days while Saurav can do it in 3days.They work together for a dayand rest of the work is done by sachin in 1day.If they get 1800 for the whole work,the wage of Sachin is

A can do a piece of work in 10 days, while B alone can do it in 15 days. They work together for 5 days and rest of the work is done by M in 2 days. If they get Rs. 9000 for the whole work, then how should they divide the money?

A can do a piece of work in 10 days, while B alone can do it in 15 days. They work together for 5 days and the rest of the work is done by C in 2 days. If they get Rs. 450 for the whole work, how should they divide the money ?

A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 3000 as wages for the whole work what are the daily wages of A, B and C respectively (in Rs.):

A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get 1500 for the whole work, the daily wages of B and C are a. Rs. 150 b. R s .225 c. R s .250 d. R s .300

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :