A can complete work in 10 days, B can co...

A can complete work in 10 days, B can complete in 15 days and C takes 30 days to complete. How many days they will take if they will work together?

A

`5` days

B

`4` days

C

`3`days

D

`2`days

लिखित उत्तर

Verified by Experts

The correct Answer is:
A