Satish can do 1/5th of a work in 5 days ...

Satish can do 1/5th of a work in 5 days while he and Ramesh together can do 9/10th of the same work in 10 days. They start the work together and work for 5 days after which Satish leaves. Find the number of days in which Ramesh alone can finish the remaining work.

Text Solution

Verified by Experts

The correct Answer is:
11
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Essay Type Question|5 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-1)|33 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS (Very Short Answer Type Questions)|30 Videos
  • TIME AND DISTANCE

    PEARSON IIT JEE FOUNDATION|Exercise Concept Application (Level 2 )|3 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.

A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A can do (1)/(5)th of a work in 4 days and B can do (1)/(6) th of the same work in 5 days. In how many days they can finish the work, if they work together?

P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?

A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?