Home
Class 8
MATHS
Fifteen men can complete a piece of work...

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the formula related to work, which states: \[ M_1 \times N_1 \times D_1 \times H_1 = M_2 \times N_2 \times D_2 \times H_2 \] Where: - \(M\) = Number of men - \(N\) = Number of days - \(D\) = Number of hours per day - \(H\) = Work done ### Step 1: Determine the total work done by the initial group of men. Given: - 15 men can complete the work in 10 days, working 8 hours per day. Total work \(W_1\) can be calculated as: \[ W_1 = M_1 \times N_1 \times D_1 \times H_1 = 15 \times 10 \times 8 \] ### Step 2: Calculate the total work \(W_1\). \[ W_1 = 15 \times 10 \times 8 = 1200 \text{ man-hours} \] ### Step 3: Since we need to complete double the work, calculate \(W_2\). \[ W_2 = 2 \times W_1 = 2 \times 1200 = 2400 \text{ man-hours} \] ### Step 4: Set up the equation for the second scenario. We need to find the number of men \(M_2\) required to complete \(W_2\) in 25 days working 6 hours per day. Using the formula: \[ M_1 \times N_1 \times D_1 \times H_1 = M_2 \times N_2 \times D_2 \times H_2 \] Substituting the known values: \[ 15 \times 10 \times 8 \times 2 = M_2 \times 25 \times 6 \] ### Step 5: Substitute \(W_2\) into the equation. \[ 2400 = M_2 \times 25 \times 6 \] ### Step 6: Solve for \(M_2\). \[ M_2 = \frac{2400}{25 \times 6} \] ### Step 7: Calculate \(M_2\). \[ M_2 = \frac{2400}{150} = 16 \] ### Conclusion: Thus, **16 persons** are required to complete double the work in 25 days, working 6 hours per day. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-1)|33 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-2)|20 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Short Answer Type Questions|15 Videos
  • TIME AND DISTANCE

    PEARSON IIT JEE FOUNDATION|Exercise Concept Application (Level 2 )|3 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?

12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?

7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?