Certain number of artisans can complete ...

Certain number of artisans can complete a shoe fabrication consignment in 16 days. 8 additional artisans had to be deployed for the same consignment and together they completed it in 4 days less than the earlier estimate. The number of artisans initially employed was `18` b. `20` c. `24` d. none of these

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

B and C can complete a piece of work in 12 days,C and A can do it in 8 days. All the three can do it in 6 days. A and B together can complete It In (A) 4 days (B) 6 days (C ) 8 days (D) 10 days

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

M can complete a work in 14 days less than the time taken by L. If both M and L together can complete the same work in 24 days, then in how many days M alone can complete the same work?

A is thrice as efficient as B and hence completes a work in 40 days less than the number days taken by B. What will be the number of days taken by both of them when working together ?

A is thrice as efficient as B and hence completes a work in 40 days less than the number of days taken by B. What will be the number of days taken by both of them when working together?

C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?

RS AGGARWAL-CHAIN RULE-All Questions
  1. If 600 men dig a 5.5 m wide, 4 m deep and 405 m long canal in half a...

    Text Solution

    |

  2. 21 binders can bind 1400 books in 15 days. How many binders will be...

    Text Solution

    |

  3. Certain number of artisans can complete a shoe fabrication consignm...

    Text Solution

    |

  4. If 9 examiners can examine a certain number of answer books in 12 d...

    Text Solution

    |

  5. If 17 labourers can dig a ditch 20 m long in 18 days working 8 hour...

    Text Solution

    |

  6. 20 men complete one- third of a piece of work in 20 days. How many ...

    Text Solution

    |

  7. A rope makes 70 rounds of the circumference of a cylinder whose rad...

    Text Solution

    |

  8. If x men, working x hours per day, can do x units of work in x days, t...

    Text Solution

    |

  9. A contract is to be completed in 46 days and 117 men were set to wor...

    Text Solution

    |

  10. The normal dosage of a particular medicine is t tablets per day for...

    Text Solution

    |

  11. Some persons can do a piece of work in 12 days. Two times the numbe...

    Text Solution

    |

  12. 12 persons can do a piece of work in 4 days. How many persons are r...

    Text Solution

    |

  13. If 5 engines consume 6 metric tonnes of coal when each is running 9...

    Text Solution

    |

  14. If 9 men working 7 1/2 hours a day can finish a piece of work in 20 da...

    Text Solution

    |

  15. If a certain number of workmen can do a piece of work in 25 hours, ...

    Text Solution

    |

  16. 15 men take 21 days of 8 hours each to do a piece of work How many ...

    Text Solution

    |

  17. A contractor employed 30 men to do a piece of work in 38 days. After...

    Text Solution

    |

  18. In a barrack of soldiers there was stock of food for 190 days for 40...

    Text Solution

    |

  19. A garrison of 500 men had provisions for 27 days. After 3 days a re...

    Text Solution

    |

  20. A garrison had provisions for a certain number of days. After 10 da...

    Text Solution

    |