A contract is to be completed in 46 days...

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, `4/7` of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? `80` b. `82` c. `81` d. `83`

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

A contract is to be completed in 50 days and 105 men were set to work,each working 8 hours a day.After 25 days,(2)/(5) of the work is finished.How many additional men are be employed so that the work many be completed on time,each man now working 9hours a day?

A contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?

RS AGGARWAL-CHAIN RULE-All Questions
  1. A rope makes 70 rounds of the circumference of a cylinder whose rad...

    Text Solution

    |

  2. If x men, working x hours per day, can do x units of work in x days, t...

    Text Solution

    |

  3. A contract is to be completed in 46 days and 117 men were set to wor...

    Text Solution

    |

  4. The normal dosage of a particular medicine is t tablets per day for...

    Text Solution

    |

  5. Some persons can do a piece of work in 12 days. Two times the numbe...

    Text Solution

    |

  6. 12 persons can do a piece of work in 4 days. How many persons are r...

    Text Solution

    |

  7. If 5 engines consume 6 metric tonnes of coal when each is running 9...

    Text Solution

    |

  8. If 9 men working 7 1/2 hours a day can finish a piece of work in 20 da...

    Text Solution

    |

  9. If a certain number of workmen can do a piece of work in 25 hours, ...

    Text Solution

    |

  10. 15 men take 21 days of 8 hours each to do a piece of work How many ...

    Text Solution

    |

  11. A contractor employed 30 men to do a piece of work in 38 days. After...

    Text Solution

    |

  12. In a barrack of soldiers there was stock of food for 190 days for 40...

    Text Solution

    |

  13. A garrison of 500 men had provisions for 27 days. After 3 days a re...

    Text Solution

    |

  14. A garrison had provisions for a certain number of days. After 10 da...

    Text Solution

    |

  15. A fort has provisions for 50 days. If after 10 days they are streng...

    Text Solution

    |

  16. A garrison of 2000 men has provision of ration for 66 days. At the ...

    Text Solution

    |

  17. A team of workers was employed by a contractor who undertook to fin...

    Text Solution

    |

  18. The work done by a woman in 8 hours is equal to the work done by a ...

    Text Solution

    |

  19. 12 men and 18 boys, working 7 1/2 , hours a day, can do a piece of wor...

    Text Solution

    |

  20. If 3 men or 6 boy, can do a piece of work in 10 days, working 7 hour...

    Text Solution

    |