A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? .a. `1` b. `\ 1 1/4` c. `1 3/4` d. `1 1/2`

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work finished one day earlier.How many days would it have been delayed if 5 more men were not employed?

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

If 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?

8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?

A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?

A certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?

RS AGGARWAL-CHAIN RULE-All Questions
  1. If 9 men working 7 1/2 hours a day can finish a piece of work in 20 da...

    Text Solution

    |

  2. If a certain number of workmen can do a piece of work in 25 hours, ...

    Text Solution

    |

  3. 15 men take 21 days of 8 hours each to do a piece of work How many ...

    Text Solution

    |

  4. A contractor employed 30 men to do a piece of work in 38 days. After...

    Text Solution

    |

  5. In a barrack of soldiers there was stock of food for 190 days for 40...

    Text Solution

    |

  6. A garrison of 500 men had provisions for 27 days. After 3 days a re...

    Text Solution

    |

  7. A garrison had provisions for a certain number of days. After 10 da...

    Text Solution

    |

  8. A fort has provisions for 50 days. If after 10 days they are streng...

    Text Solution

    |

  9. A garrison of 2000 men has provision of ration for 66 days. At the ...

    Text Solution

    |

  10. A team of workers was employed by a contractor who undertook to fin...

    Text Solution

    |

  11. The work done by a woman in 8 hours is equal to the work done by a ...

    Text Solution

    |

  12. 12 men and 18 boys, working 7 1/2 , hours a day, can do a piece of wor...

    Text Solution

    |

  13. If 3 men or 6 boy, can do a piece of work in 10 days, working 7 hour...

    Text Solution

    |

  14. 2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys c...

    Text Solution

    |

  15. Large, medium and small ships are used to bring water. 4 large ships...

    Text Solution

    |

  16. If 2m 60 m cloth is required for one shirt then the cloth required for...

    Text Solution

    |

  17. The cost of 4 dozen papers is Rs. 24. The cost of 1 score of papers ...

    Text Solution

    |

  18. The cost of 8 fans and 14 ovens Rs. 36.520. What is the cost of 12 ...

    Text Solution

    |

  19. The cost of 5 kgs, of apples is Rs. 450. The cost of 12 dozen mangoe...

    Text Solution

    |

  20. The cost of 21 pencils and 9 clippers is Rs. 819. The cost price of...

    Text Solution

    |