A, B and C get Rs. 5400 for doing a work...

A, B and C get Rs. 5400 for doing a work in 36 days. A and C get Rs. 1880 for doing the same work in 20 days, while B and C get Rs. 3040 for doing the same work in 40 days. Find the amount received by C per day.

A

Rs. 50

B

Rs. 25

C

Rs. 30

D

Rs. 20

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE BASE LEVEL QUESTIONS|17 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos

Similar Questions

Explore conceptually related problems

A and B together can do work in 20 days, B and and C and do the same work in 60 days. Who is the most efficient among A,B and C?

A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

A and C can do a work in 12 days while A,B and C can do the work in 4 days. In how many days can B do the work alone?

B and C can do a certain work in 35 days, while A,B and C can do the same work in 17.5 days. In how many days can A do the same work alone?

A and B can do a certain work in 12 days. B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work?

4 men and 6 women get Rs. 1600 by doing a piece of work in 5 days. 3 men and 7 women get Rs. 1740 by doing the same work in 6 days. In how many days, 7 men and 6 women can complete the same work getting Rs. 3760?

A and B can do a certain work in 12 days, B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work ?