A can complete (2)/(3) of work in 6 days...

A can complete `(2)/(3)` of work in 6 days. In what time can he complete `(4)/(9)` of the work ?

Promotional Banner

Similar Questions

Explore conceptually related problems

A completes (2)/(3) of a certain job in 6 days. B can complete (1)/(3) of the same job in 8 days and C can complete (3)/(4) of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?

Time taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?

If Ramesh can complete 2/5th of a work in 24 days and Satish can complete 1/3rd of the work in 30 days, then in how many days can they complete the work if they work together?

If Ramesh can complete 2/5th of a work in 24 days and Satish can complete 1/3rd of the work in 30 days, then in how many days can they complete the work if they work together?

A can complete of a work in 8 days. B can complete 3/5 of the same work in 12 days and C can complete 4/9 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?