[" 129.A and "B" can do a piece of work ...

[" 129.A and "B" can do a piece of work in "3" days,"B" and "],[" Cin "4" days,"C" and "A" in "4" days.The time taken "],[" by "C" alone to do it is "],[[" (a) "16" days "," (b) "25" days "],[" (c) "20" days "," (d) "24" days "]]

Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days. In what time can each finish it working alone ?

A and B can do a piece of work in 12 days, B and C in 15 days C and A in 20 days. In how many days can C alone do it ?

A and B can do a piece of wok in 72 days, B and C can do it in 120 days, A and C can do it in 90 days. In what time can A alone do it ?