If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?

A

30

B

10

C

18

D

28

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Similar Questions

Explore conceptually related problems

If 24 workers can build a wall in 15 days, how many days will 8 workers take to build a similar wall?

40 men can build a wall 200 m longin 12 days working 8 h a day. The number of days 30 men will take to build a similar wall 300 m long working 6h per day will be (A) 32 (B) 18 (C) 36 (D) 9

15 men can build a 16.25 -m- long wall up to a certainj height in one day. How many men should be employed to build a wall of the same height but of length 26 metres in one day?

40 men build a well 20 m high in 15 days. The number of men required to build a similar wall 25 m high in 6 days will be:

24 workers can build a wall in 15 days. How many days will 9 workers take to build a similar wall?