S,T and U can complete a work in 40,48 and 60 days respectively. They received Rs. 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work along. What is the share of S ( in Rs. ) from total money ?

A

4000

B

4320

C

4500

D

4860

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the total work The total work can be calculated using the Least Common Multiple (LCM) of the days taken by S, T, and U to complete the work. - S can complete the work in 40 days. - T can complete the work in 48 days. - U can complete the work in 60 days. To find the LCM of 40, 48, and 60: - Prime factorization: - 40 = 2^3 * 5 - 48 = 2^4 * 3 - 60 = 2^2 * 3 * 5 The LCM will take the highest power of each prime factor: - LCM = 2^4 * 3^1 * 5^1 = 240 Thus, the total work is 240 units. ### Step 2: Calculate the work done by each person in one day Now, we will calculate how much work each person can do in one day. - Work done by S in one day = Total work / Days taken by S = 240 / 40 = 6 units - Work done by T in one day = Total work / Days taken by T = 240 / 48 = 5 units - Work done by U in one day = Total work / Days taken by U = 240 / 60 = 4 units ### Step 3: Calculate the combined work done in one day The combined work done by S, T, and U in one day is: - Total work done in one day = Work by S + Work by T + Work by U = 6 + 5 + 4 = 15 units ### Step 4: Determine the total time taken to complete the work Let X be the total number of days taken to complete the work. - S worked for X days. - T worked for (X - 2) days (since T left 2 days before completion). - U worked for (X - 5) days (since U left 5 days before completion). The equation for the total work done is: \[ 6X + 5(X - 2) + 4(X - 5) = 240 \] Expanding this: \[ 6X + 5X - 10 + 4X - 20 = 240 \] \[ 15X - 30 = 240 \] \[ 15X = 270 \] \[ X = 18 \] ### Step 5: Calculate the work done by each person Now we can calculate how much work each person completed: - Work done by S = 6 * 18 = 108 units - Work done by T = 5 * (18 - 2) = 5 * 16 = 80 units - Work done by U = 4 * (18 - 5) = 4 * 13 = 52 units ### Step 6: Calculate the total work done Total work done = Work by S + Work by T + Work by U = 108 + 80 + 52 = 240 units (which confirms our calculations). ### Step 7: Calculate the share of S from the total money The total money received is Rs. 10800. The share of each person is proportional to the work done. - Total work done = 240 units - Share of S = (Work done by S / Total work) * Total money \[ \text{Share of S} = \left(\frac{108}{240}\right) \times 10800 \] \[ \text{Share of S} = \frac{108 \times 10800}{240} \] \[ \text{Share of S} = \frac{1166400}{240} = 4860 \] ### Final Answer The share of S from the total money is **Rs. 4860**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24

A,B and C can complete a work in 10,12 and 15 days respectively.They started the work together.But A left the work 5 days before its completion.B also left the work 2 days after A left.In how many days was the work completed? 4 b.15 c.7 d.8