Home
Class 14
MATHS
A work could be completed in 100 days by...

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:

A

100

B

110

C

55

D

50

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these instructions: ### Step 1: Define the variables Let the original number of workers be \( X \). ### Step 2: Set up the equation for the work done If \( X \) workers can complete the work in 100 days, then the total work can be expressed in terms of worker-days: \[ \text{Total Work} = X \times 100 \] ### Step 3: Set up the equation for the work done with fewer workers If 10 workers are absent, then the number of workers becomes \( X - 10 \). These workers complete the same amount of work in 110 days: \[ \text{Total Work} = (X - 10) \times 110 \] ### Step 4: Set the two expressions for total work equal to each other Since both expressions represent the same total work, we can set them equal: \[ X \times 100 = (X - 10) \times 110 \] ### Step 5: Expand and simplify the equation Expanding the right side: \[ 100X = 110X - 1100 \] ### Step 6: Rearrange the equation to isolate \( X \) Now, let's move all terms involving \( X \) to one side and the constant to the other side: \[ 100X - 110X = -1100 \] \[ -10X = -1100 \] ### Step 7: Solve for \( X \) Dividing both sides by -10 gives: \[ X = \frac{1100}{10} = 110 \] ### Conclusion The original number of workers was \( 110 \). ---
Promotional Banner

Similar Questions

Explore conceptually related problems

If 15 workers can earn ₹1,800 in 10 days. Find the earning (in ₹) of 5 workers in 8 days.

A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?

How many workers are required for completing the construction work in the 10 days ? (i) 20% of the work can be completed by 8 workers in 8 days. (ii) 20 workers can complete the work in 16 days. (iii) One - eighth of the work can ve completed by 8 workers in 5 days.

42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.