Home
Class 14
MATHS
A and B can do a piece of work in 12 day...

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone?

A

24 days

B

32 days

C

40 days

D

48 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how long B would take to complete the work alone based on the information given about the work done by A, B, and C together. Here’s a step-by-step breakdown of the solution: ### Step 1: Determine the total work We know that: - A and B can complete the work in 12 days. - B and C can complete the work in 8 days. - C and A can complete the work in 6 days. To find a common measure of work, we can take the Least Common Multiple (LCM) of the days taken by each pair to complete the work. The LCM of 12, 8, and 6 is 24. Therefore, we can consider the total work to be 24 units. ### Step 2: Calculate the work done by each pair in one day Now we can find the work done by each pair in one day: - Work done by A and B in one day = Total work / Days = 24 / 12 = 2 units. - Work done by B and C in one day = Total work / Days = 24 / 8 = 3 units. - Work done by C and A in one day = Total work / Days = 24 / 6 = 4 units. ### Step 3: Set up equations based on the work done Let: - A's work in one day = a - B's work in one day = b - C's work in one day = c From the above calculations, we can set up the following equations: 1. \( a + b = 2 \) (Equation 1) 2. \( b + c = 3 \) (Equation 2) 3. \( c + a = 4 \) (Equation 3) ### Step 4: Solve the equations We can add all three equations: \[ (a + b) + (b + c) + (c + a) = 2 + 3 + 4 \] This simplifies to: \[ 2a + 2b + 2c = 9 \] Dividing by 2 gives: \[ a + b + c = 4.5 \] (Equation 4) Now we can find the individual work rates: From Equation 1: \[ c = 4.5 - (a + b) = 4.5 - 2 = 2.5 \] Substituting \( c \) back into Equation 2: \[ b + 2.5 = 3 \] Thus, \[ b = 3 - 2.5 = 0.5 \] Now substituting \( b \) into Equation 1: \[ a + 0.5 = 2 \] Thus, \[ a = 2 - 0.5 = 1.5 \] ### Step 5: Calculate B's time to complete the work alone Now we have: - A's work rate (a) = 1.5 units/day - B's work rate (b) = 0.5 units/day - C's work rate (c) = 2.5 units/day To find out how long B would take to complete the entire work alone (24 units), we use the formula: \[ \text{Time} = \frac{\text{Total Work}}{\text{B's Work Rate}} \] \[ \text{Time} = \frac{24}{0.5} = 48 \text{ days} \] ### Final Answer B would take **48 days** to complete the work alone. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?

A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

A and B can do a piece of work in 12 days, B and C in 15 days C and A in 20 days. In how many days can C alone do it ?

A and B can do a piece of work in 10 days.B and C can do it in 12 days. A and C can do it in 15 days. How long will A take to do it alone?

A and B can do a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can each alone do the work?